How this estimate is calculated
Commercial CAPEX Calculator · calculation version 3.0.0 · reviewed 2026-08-21 by FishMatch Group technical editorial team · confidence: planning estimate
Planning estimate only. Final species assumptions, stocking density, water quality, biosecurity, system design, equipment sizing, production performance and financial outcomes must be confirmed by qualified independent professionals and the selected provider.
Purpose
Build an indicative CAPEX range from the buyer's own scope selections and unit inputs.
How it was calculated
- equipment_capex = Σ(selected scope line items × entered unit rates)
- installed_capex = equipment_capex + installation + freight + duties
- total_project_capex = installed_capex + civil works + buildings + commissioning + training + contingency + initial working capital (where entered)
Where each value comes from
- Project scope
- Buyer input
- Capacity
- Buyer input
- Contingency
- Buyer input
What the outputs mean
- Equipment-only CAPEX
- Installed CAPEX
- Total project CAPEX including contingency
Limitations
- No single $/tonne CAPEX benchmark is universally applicable. Any headline figure shown is the direct arithmetic result of the inputs on screen, not a market benchmark.
- Land is included only when the buyer enters it.
- Freight, duties and local civil-works costs vary by country and by year and must be quoted.
What must be confirmed before you build
- Supplier quotations for every equipment line
- Local civil works and construction pricing
- Freight, duty and import tax
- Commissioning and training scope
Sources for default assumptions
Next step
Review every value above, correct anything that does not match your site, then transfer the reviewed figures into a structured RFQ. Nothing is sent to any supplier until you approve it. Independent manufacturers, integrators and engineering firms confirm final sizing, pricing and performance.