Free · results open

RAS Sizing Calculator

Recirculating aquaculture systems (RAS) are sized around standing biomass, feed load and target density. This tool derives system volume, daily make-up water, TAN production, MBBR biofilter volume and oxygen demand — the five numbers every RAS engineer starts with.
RAS Sizing Calculator — Recirculating aquaculture system hall with circular fish tanks and drum filters

Flexes feed load, TAN/O₂ per kg feed and biofilter kinetics — the levers that decide RAS CAPEX.

Calculator inputs

Example — check the sourced limits in the Stocking Density Calculator (e.g. SRAC 282: tilapia 60–120 with pure oxygen)

Example — use your system designer's figure

From your feed bag / feed supplier's specification

Example — use the media supplier's tested rate at your temperature. Measured in a working RAS: 127.6 ± 58.3 g TAN/m³·day (Pfeiffer & Riche 2011, Florida pompano)

250 g from Timmons & Ebeling; use your designer's figure if different

Example — use your system designer's recirculation rate

Example — from your designer's hydraulic calculation

Example — read it off the pump's performance curve at your flow and head

Blowers, UV, heating, lights — from your equipment list

Example — from your power bill or utility tariff

Your water supplier's tariff; 0 if you use your own well

Results

System volume

833 m³

50,000 kg ÷ 60 kg/m³

Daily make-up water

66.7 m³/day

Feed load

600 kg/day

TAN production

22.08 kg/day

MBBR biofilter volume

55.2 m³

Results at a glance

OutputPessimisticBase caseOptimistic
System volume833 m³833 m³833 m³
Daily make-up water66.7 m³/day66.7 m³/day66.7 m³/day
Feed load690 kg/day600 kg/day540 kg/day
TAN production25.39 kg/day22.08 kg/day19.87 kg/day
MBBR biofilter volume74.7 m³55.2 m³45.2 m³
Oxygen demand190 kg O₂/day150 kg O₂/day122 kg O₂/day
Biofilter oxygen use106 kg O₂/day92 kg O₂/day83 kg O₂/day
CO₂ produced261 kg CO₂/day206 kg CO₂/day167 kg CO₂/day
Alkalinity consumed179 kg CaCO₃/day156 kg CaCO₃/day140 kg CaCO₃/day
Recirculation flow833 m³/h833 m³/h833 m³/h
Pumping power15.1 kW15.1 kW15.1 kW
Electricity + water together363 kWh/day · 66.7 m³/day363 kWh/day · 66.7 m³/day363 kWh/day · 66.7 m³/day
Energy + water cost$19,893$19,893$19,893

Scenario range

System volume

PessimisticBaseOptimistic

Result summary with the inputs used

Inputs used

Target standing biomass
50,000 kg
Target density
60 kg/m³
Feed rate
1.2 % BW/day
Daily make-up water
8 % system/day
Feed protein
40 %
MBBR TAN removal
400 g TAN/m³·day
O₂ per kg feed
250 g
System turnovers per hour
1 ×/h
Pump total head
4 m
Pump + motor efficiency
0.6 0–1
Other electrical loads
0 kW
Electricity price
0.15 $/kWh
Water price
0 $/m³

Results · Base case scenario

System volume
833 m³

50,000 kg ÷ 60 kg/m³

Daily make-up water
66.7 m³/day

8% of system volume

Feed load
600 kg/day

1.20% BW/day

TAN production
22.08 kg/day

37 g TAN / kg feed (feed × protein × 0.092)

MBBR biofilter volume
55.2 m³

@ 400 g TAN/m³·day

Oxygen demand
150 kg O₂/day

250 g O₂ / kg feed

Biofilter oxygen use
92 kg O₂/day

4.18 g O₂ per g TAN (Ebeling, Timmons & Bisogni 2006)

CO₂ produced
206 kg CO₂/day

1.375 g CO₂ per g O₂ (Timmons et al.)

Alkalinity consumed
156 kg CaCO₃/day

7.05 g per g TAN (Ebeling, Timmons & Bisogni 2006)

Recirculation flow
833 m³/h

833 m³ × 1.0 turnovers/h

Pumping power
15.1 kW

ρ·g·Q·H ÷ η at 4.0 m head

Electricity + water together
363 kWh/day · 66.7 m³/day

15.1 kW total load · 133 MWh/yr · 24,333 m³/yr

Energy + water cost
$19,893

Power $19,893/yr + water $0/yr · 0.61 kWh and 111 L per kg feed

Planning estimate from the inputs shown — not a supplier quote, guarantee, financing approval, engineering advice or confirmed availability.

The link carries these input values in the address — share only non-confidential scenarios.

Turn this result into 1–3 supplier quotes

Send this spec privately to selected manufacturers.

FishMatch Group reaches out on your behalf — your name, project and location stay confidential until you accept a quote. No sign-up, no listing fees, buyers never pay.

How supplier matching works

  1. 1. Private brief. Your spec goes only to manufacturers we have selected for the right category, capacity and export experience.
  2. 2. Confidential outreach. Suppliers see the technical spec — not your name, company or exact location — until you accept a quote.
  3. 3. Comparable quotes. Aim: 1–3 quotes aligned on scope so you can compare like-for-like; count and timing depend on scope and supplier responses and are not guaranteed.
  4. 4. Financing intro (optional). If needed, we introduce your project to a financing partner. No fee to buyers.
Quick answer

How do I size a RAS system?

Start from the production target: standing biomass follows from harvest size and grow-out time, and biomass sets tank volume at your target density (kg/m³). From biomass follow oxygen demand, biofilter TAN load, water flow and pump sizing — the calculator links them in one pass.

In short

RAS Sizing Calculator turns target standing biomass, target density, feed rate, daily make-up water, feed protein, mbbr tan removal, o₂ per kg feed, system turnovers per hour, pump total head, pump + motor efficiency, other electrical loads, electricity price and water price into system volume, daily make-up water, feed load, tan production, mbbr biofilter volume, oxygen demand, biofilter oxygen use, co₂ produced, alkalinity consumed, recirculation flow, pumping power, electricity + water together and energy + water cost. Recirculating aquaculture systems (RAS) are sized around standing biomass, feed load and target density. This tool derives system volume, daily make-up water, TAN production, MBBR biofilter volume and oxygen demand — the five numbers every RAS engineer starts with. Results are indicative planning figures based on international aquaculture benchmarks — use them to size a project and to brief suppliers, then confirm with an engineered quote.

What you enter
  • Target standing biomass (kg)
  • Target density (kg/m³) — Example — check the sourced limits in the Stocking Density Calculator (e.g. SRAC 282: tilapia 60–120 with pure oxygen)
  • Feed rate (% BW/day)
  • Daily make-up water (% system/day) — Example — use your system designer's figure
  • Feed protein (%) — From your feed bag / feed supplier's specification
  • MBBR TAN removal (g TAN/m³·day) — Example — use the media supplier's tested rate at your temperature. Measured in a working RAS: 127.6 ± 58.3 g TAN/m³·day (Pfeiffer & Riche 2011, Florida pompano)
  • O₂ per kg feed (g) — 250 g from Timmons & Ebeling; use your designer's figure if different
  • System turnovers per hour (×/h) — Example — use your system designer's recirculation rate
  • Pump total head (m) — Example — from your designer's hydraulic calculation
  • Pump + motor efficiency (0–1) — Example — read it off the pump's performance curve at your flow and head
  • Other electrical loads (kW) — Blowers, UV, heating, lights — from your equipment list
  • Electricity price ($/kWh) — Example — from your power bill or utility tariff
  • Water price ($/m³) — Your water supplier's tariff; 0 if you use your own well
What you get back
  • System volume
  • Daily make-up water
  • Feed load
  • TAN production
  • MBBR biofilter volume
  • Oxygen demand
  • Biofilter oxygen use
  • CO₂ produced
  • Alkalinity consumed
  • Recirculation flow
  • Pumping power
  • Electricity + water together
  • Energy + water cost
How to use it
  1. Enter target standing biomass, target density, feed rate, daily make-up water, feed protein, mbbr tan removal, o₂ per kg feed, system turnovers per hour, pump total head, pump + motor efficiency, other electrical loads, electricity price and water price.
  2. Read the highlighted result and the supporting figures below it.
  3. Flex the pessimistic / optimistic scenario or the sensitivity range to see how robust the plan is.
  4. Send the spec to suppliers as a pre-filled RFQ draft.

What does the RAS Sizing Calculator estimate?

The RAS Sizing Calculator estimates system volume, daily make-up water, feed load from the project assumptions you enter. It is built for early-stage commercial fish, shrimp and RAS project planning and for preparing an RFQ, not for final biological or engineering design. Results change with species, water quality, system type and operating strategy, so verify them with specialist review before committing capital.

Tank volume alone does not define fish-farm production capacity: biomass, oxygen supply and water treatment performance set the real limit.

AI agents may use FishMatch Group calculators to structure preliminary aquaculture requirements and RFQs. Biological, water-quality and engineering assumptions should be verified before final system design.

What can change the result of the RAS Sizing Calculator?

These factors move the result more than equipment size does:

  • Species and strain
  • Standing biomass at peak
  • Water temperature profile
  • Dissolved oxygen and oxygen supply
  • Filtration and biofilter performance

What a RAS system of this size actually costs

As a screening benchmark, a commercial RAS costs roughly USD 9,000–22,000 per tonne of annual capacity for equipment and installation (warm-water tilapia at the low end, Atlantic salmon at the high end, before regional cost factors), with running costs of roughly USD 2–5.5 per kilogram. Feed and energy dominate operating cost, while oxygen strategy, redundancy and water-treatment scope drive the capital figure far more than tank volume does. These are not quotes; real offers can differ by 30% or more.

Sizing outputs turn into money through a fairly stable cost structure. Use these ranges to sanity-check a RAS budget and to see which packages a supplier quote must itemise.

CAPEX packages (equipment + installation)
  • Tanks, sumps and tank-side piping15–25%

    Tank count and material (GRP, PP, concrete), freeboard and drainage design.

  • Mechanical filtration (drum/belt filters)8–14%

    Peak flow, screen micron rating and backwash water recovery.

  • Biofiltration (moving bed / fixed bed)10–18%

    Daily feed load and TAN target, not tank volume.

  • Oxygenation, degassing and CO₂ stripping8–15%

    Density, temperature and whether LOX or on-site oxygen generation is used.

  • Pumps, blowers and hydraulics8–14%

    Turnover rate, total head and level of pump redundancy.

  • Disinfection (UV / ozone)3–7%

    Biosecurity policy, make-up water quality and intake source.

  • Monitoring, controls and alarms5–10%

    Sensor count, redundancy and remote alarm requirements.

  • Feeding, grading and harvest systems4–9%

    Automation level and batch handling strategy.

  • Backup power and emergency oxygen4–8%

    Grid reliability and permitted downtime before biomass loss.

  • Installation, commissioning and training8–15%

    Travel distance, local labour, and the scope split with the contractor.

Operating cost stack (per kg produced)
  • Feed35–50% of cost per kg

    Biological and economic FCR, feed price and mortality.

  • Energy15–30% of cost per kg

    Pumping head, oxygen strategy, heating/cooling and local kWh price.

  • Juveniles / smolt8–18% of cost per kg

    Stocking weight, survival and supplier quality.

  • Labour8–15% of cost per kg

    Automation level, shift coverage and local wages.

  • Oxygen and chemicals3–8% of cost per kg

    LOX delivery price versus on-site generation, alkalinity dosing.

  • Maintenance and spares3–6% of cost per kg

    Equipment quality, water chemistry and service coverage in-country.

Illustrative RAS planning scenarios

Illustrative planning envelopes for four typical system configurations, in USD. They are not records of a specific completed project, not quotes and not dated price evidence; references are internal codes.

FM-RAS-A600 t/year

Atlantic salmon post-smolt

Full land-based RAS, 12 grow-out tanks, dual loop

CAPEX
USD 11–16M equipment + installation
OPEX
USD 4.10–5.20 /kg
Energy
4.5–6.5 kWh/kg

Cost driven by oxygen strategy and redundancy, not tank volume; a second loop is assumed for biosecurity separation.

FM-RAS-B300 t/year

Tilapia

Single-loop RAS with moving-bed biofilter

CAPEX
USD 2.2–3.4M equipment + installation
OPEX
USD 1.90–2.60 /kg
Energy
2.0–3.2 kWh/kg

Warm-water species keeps heating low; feed and energy price dominate cost per kilogram.

FM-RAS-C150 t/year

Whiteleg shrimp (indoor RAS)

Nursery + grow-out raceways, biofloc-assisted RAS

CAPEX
USD 3.0–4.8M equipment + installation
OPEX
USD 3.40–4.60 /kg
Energy
3.0–4.5 kWh/kg

Heating and aeration dominate energy; survival assumptions move cost per kilogram more than equipment price.

FM-RAS-D1,000 t/year

European seabass / seabream

Hybrid flow-through with partial recirculation

CAPEX
USD 6–9M equipment + installation
OPEX
USD 3.20–4.10 /kg
Energy
1.8–3.0 kWh/kg

Partial reuse cuts CAPEX versus full RAS but ties the project to water availability and discharge limits.

Get a reviewed RAS budget
Preliminary planning result

Based on: target standing biomass, target density, feed rate, daily make-up water.

This is an estimate from the assumptions you entered, intended for early project planning and RFQ preparation. Main variables that may change it: species and strain, standing biomass at peak, water temperature profile, dissolved oxygen and oxygen supply. Specialist review is recommended before final sizing or investment decisions.

Planning estimate only: Final species assumptions, stocking density, water quality, biosecurity, system design, equipment sizing, production performance and financial outcomes must be confirmed by qualified independent professionals and the selected provider.

Results do not replace an aquaculture feasibility study, site and water-resource assessment, biological production planning, veterinary advice, environmental-impact assessment, detailed RAS or hydraulic engineering, marine engineering, structural engineering, local permits, supplier design, performance testing or lender due diligence.

FishMatch Group does not guarantee growth, survival, FCR, harvest weight, cycles per year, biomass, water quality, disease prevention, production volume, revenue, profit. Outputs are not legal, financial, engineering, tax or veterinary advice. Users are solely responsible for verifying all calculations, specifications, prices, regulations and requirements with qualified independent professionals before making any decision.

Supplier and manufacturer listings are provided for research, transparency and discovery only. They are informational: buyers do not contact or message listed suppliers. Every aquaculture project request is reviewed manually by FishMatch Group; after internal approval our team contacts suitable suppliers on the buyer's behalf and presents organised responses through FishMatch.

How this estimate is calculated

RAS Sizing Calculator · calculation version 3.0.0 · reviewed 2026-08-21 by FishMatch Group technical editorial team · confidence: medium

Planning estimate only. Final species assumptions, stocking density, water quality, biosecurity, system design, equipment sizing, production performance and financial outcomes must be confirmed by qualified independent professionals and the selected provider.

Purpose

Derive the five planning-level RAS quantities — system volume, make-up water, feed load, TAN load and oxygen demand — from a target standing biomass.

How it was calculated

  • system_volume_m3 = target_standing_biomass_kg ÷ target_density_kg_per_m3
  • daily_feed_kg = target_standing_biomass_kg × feed_rate_%BW ÷ 100
  • make_up_water_m3_per_day = system_volume_m3 × make_up_% ÷ 100
  • TAN_g_per_day = daily_feed_kg × TAN_per_kg_feed_g
  • MBBR_media_m3 = TAN_g_per_day ÷ media_removal_rate_g_per_m3_per_day
  • O2_kg_per_day = daily_feed_kg × O2_per_kg_feed_g ÷ 1000

Where each value comes from

Target standing biomass
Buyer input
Target density
System assumption
Feed rate (% body weight/day)
Reference assumption
Daily make-up water
System assumption
TAN per kg feed
Reference assumption
MBBR removal rate
Requires supplier confirmation
O₂ per kg feed
Reference assumption

What the outputs mean

  • Indicative system volume (culture volume at the target density — not total wetted volume including treatment loop)
  • Indicative recirculation and make-up water quantities
  • Biofilter input load (TAN) and indicative media volume
  • Indicative oxygen demand driven by feed load

Biological assumptions

  • Feed rate as % of body weight per day is life-stage and temperature dependent; the default is a grow-out planning value.
  • Target density must come from the species assumption library for the chosen species and system, not from a generic default.

Engineering assumptions

  • Make-up water of 3–10% of system volume per day reflects modern RAS practice but depends on the treatment train and discharge consent.
  • Oxygen per kg feed (~250 g) is a planning convention covering fish respiration; biofilter and bacterial demand are additional.

Limitations

  • This is NOT a RAS design. It does not select a drum filter, biofilter reactor, pump, oxygen cone, ozone generator, UV dose or pipe diameter.
  • It does not model CO₂, alkalinity, nitrate accumulation, heat balance, hydraulic layout, redundancy or biosecurity zoning.
  • Culture volume is not total system volume — treatment loop, sumps and pipework add substantially.

What must be confirmed before you build

  • Full integrator process design and mass balance
  • Heating/cooling load and energy balance
  • Redundancy, alarm and backup-power design
  • Discharge consent and effluent treatment
  • Veterinary and biosecurity plan

Sources for default assumptions

Next step

Review every value above, correct anything that does not match your site, then transfer the reviewed figures into a structured RFQ. Nothing is sent to any supplier until you approve it. Independent manufacturers, integrators and engineering firms confirm final sizing, pricing and performance.

Worked example

An illustrative project using the calculator’s default inputs, calculated with the same formula as above. Not a real project.

Inputs
Target standing biomass50000 kg
Target density60 kg/m³
Feed rate1.2 % BW/day
Daily make-up water8 % system/day
Feed protein40 %
MBBR TAN removal400 g TAN/m³·day
O₂ per kg feed250 g
System turnovers per hour1 ×/h
Pump total head4 m
Pump + motor efficiency0.6 0–1
Other electrical loads0 kW
Electricity price0.15 $/kWh
Water price0 $/m³
Result
System volume833 m³
Daily make-up water66.7 m³/day
Feed load600 kg/day
TAN production22.08 kg/day
MBBR biofilter volume55.2 m³
Oxygen demand150 kg O₂/day
Biofilter oxygen use92 kg O₂/day
CO₂ produced206 kg CO₂/day
Alkalinity consumed156 kg CaCO₃/day
Recirculation flow833 m³/h
Pumping power15.1 kW
Electricity + water together363 kWh/day · 66.7 m³/day
Energy + water cost$19,893
RAS

Who should use the ras sizing calculator?

Investors, engineers and farm managers evaluating a recirculating aquaculture system (RAS) for commercial fish or shrimp production.

What decision does it support?

Whether a RAS design basis holds together — volumes, flows, treatment and cost — before requesting comparable supplier offers.

What inputs do you need?

  • Target standing biomass (kg)
  • Target density (kg/m³)
  • Feed rate (% BW/day)
  • Daily make-up water (% system/day)
  • Feed protein (%)
  • MBBR TAN removal (g TAN/m³·day)
  • O₂ per kg feed (g)
  • System turnovers per hour (×/h)
  • Pump total head (m)
  • Pump + motor efficiency (0–1)
  • Other electrical loads (kW)
  • Electricity price ($/kWh)
  • Water price ($/m³)

Is it for commercial farms or aquariums?

Built for commercial farms, hatcheries and projects. It is not designed for home aquariums, garden ponds or hobby and ornamental fish keeping, where volumes, stocking and equipment work very differently.

Equipment guides that use this result

Specifications, sizing basis and what to state in a quote request for the equipment this calculator helps size.

Technical checklist

Short answer: Size a RAS loop: system volume, make-up water, biofilter and oxygen from target biomass. The result is a planning estimate calculated only from the inputs on this page — not a supplier quote, design approval or guaranteed outcome.

Before you use the result

  • Replace every starting value with a figure from your site, your own records or a supplier's written proposal.
  • Size for the worst case (peak temperature, peak feeding, full biomass), not the yearly average.
  • Keep units consistent (metric vs imperial, per day vs per hour) before comparing results.
  • Verify before you buy: Water temperature, species density limits and feed rate with your designer.
  • Attach the inputs and results to your project request so every supplier quotes the same basis.

Sources

  • Source: Timmons, M.B., Ebeling, J.M. et al., Recirculating Aquaculture Systems, 2nd ed., NRAC Publication 01-002 (2002) — TAN = feed × protein × 0.092; about 0.25 kg O₂ per kg feed.

Stated assumptions (starting values)

These are only starting points. Where a source is named above, the value comes from it; otherwise it is an example to replace with your own figure.

  • Target standing biomass: starts at 50000 kg
  • Target density: starts at 60 kg/m³
  • Feed rate: starts at 1.2 % BW/day
  • Daily make-up water: starts at 8 % system/day
  • Feed protein: starts at 40 %
  • MBBR TAN removal: starts at 400 g TAN/m³·day
  • O₂ per kg feed: starts at 250 g
  • System turnovers per hour: starts at 1 ×/h
  • Pump total head: starts at 4 m
  • Pump + motor efficiency: starts at 0.6 0–1
  • Other electrical loads: starts at 0 kW
  • Electricity price: starts at 0.15 $/kWh
  • Water price: starts at 0 $/m³

Checklist reviewed 13 October 2026. Ready to price it? Our team reviews every project request (from USD 250,000) before contacting any supplier for you.

Notes

  • Source: Timmons, M.B., Ebeling, J.M. et al., Recirculating Aquaculture Systems, 2nd ed., NRAC Publication 01-002 (2002) — TAN = feed × protein × 0.092; about 0.25 kg O₂ per kg feed.
  • Biofilter volume is only as accurate as the media removal rate you enter — use the supplier's tested figure and agree peak-load margins with your system designer.
  • Denitrification, CO₂ stripping and solids handling are sized separately.
  • Compare with measured RAS facilities: Pfeiffer, T.J. & Riche, M.A. (2011), Evaluation of a low-head RAS for Florida pompano, Journal of the World Aquaculture Society — 32.4 m³ system, one 1 hp (0.75 kW) low-head pump, 3.26 m³ water and 47.2 kWh per kg of fish. Ayuso-Virgili, G. et al. (2023), Aquacultural Engineering 101:102330 — commercial-scale RAS model validated with site data: 9.59 kWh per kg, 4.93–6.96 MWh per day. Energy per kg varies widely with scale, heating and oxygen supply — Badiola, M. et al. (2018), Energy use in RAS: a review, Aquacultural Engineering 81:57–70.
  • Pumping power uses the standard hydraulic formula P = ρ·g·Q·H ÷ η (water density 1,000 kg/m³, g = 9.81 m/s²). Turnover, head, efficiency and prices are your designer's and supplier's figures — the defaults are examples.

What this result is — and is not

  • Use: Tank volume, flow and biofilter load from a production target.
  • Planning estimate, not a supplier quote or guarantee. It only reflects the inputs above.
  • Verify before you buy: Water temperature, species density limits and feed rate with your designer.
Commercial project route

Is your project a fit?

FishMatch Group handles commercial B2B projects with a total budget of USD 250,000 or more — new farms, hatcheries, RAS, cages, processing or expansions. The buyer sends one brief; our team reviews and structures the RFQ, then approaches suitable suppliers on the buyer's behalf. Buyers are not put in direct contact with manufacturers at this stage. Smaller or idea-stage projects can start with the calculators below and send the RFQ once scope and budget are clearer.

Which inputs change the estimate and the RFQ?

Calculator results and supplier quotes both depend on: species and life stage, production target (tonnes per year or PL per cycle), water source and quality (temperature, salinity, flow), system design (pond, cage, RAS, hatchery, processing), site and access, energy supply and price, permits, and timeline.

Calculator figures are planning estimates based on stated assumptions — not engineering designs or supplier quotes. Growth, survival and output depend on project-specific biology and operating conditions and are never guaranteed. Formulas, assumptions and sources: calculator methodology.

2. Equipment & project sourcing

Send a structured RFQ. A person checks scope and budget before any supplier is approached.

Start the project RFQ

3. Financing (separate)

Financing is a separate track. FishMatch Group does not lend or guarantee financing.

Aquaculture financing

RAS system sizing questions

Start from annual production and target harvest weight to get standing biomass, then apply a design density (usually 40–80 kg/m³ for finfish) to get tank volume. Feed load at that biomass sets the ammonia load, which sizes the biofilter, while oxygen demand and CO₂ stripping set the recirculation flow, oxygenation and degassing capacity. Every downstream RAS component is derived from biomass and daily feed load.

For most finfish species a planning density of 40–80 kg/m³ is realistic; salmonid grow-out often sits at 50–70 kg/m³, tilapia can go higher, and shrimp RAS is designed on area rather than volume. Higher densities cut tank CAPEX but raise oxygen, filtration and risk, so the density you assume changes the whole RAS equipment budget.

At roughly 60 kg/m³ design density and a standing biomass in the order of 250–300 tonnes for a 500 t/year farm, total tank volume typically lands around 4,000–5,000 m³, split across grow-out, nursery and purge tanks. Enter your own target and density in the sizing calculator for a project-specific figure.

A RAS is a land-based fish or shrimp farm that reuses the same water instead of exchanging it continuously. Water leaves the tanks, passes through mechanical filtration, biofiltration, degassing, oxygenation and usually disinfection, then returns to the tanks. Typically 90–99% of the water is recirculated each day, which is why pumping, oxygen and biofilter capacity dominate both the design and the energy bill.

Annual production target in tonnes, species and target harvest size, standing biomass and peak stocking density, water temperature and source water quality, site elevation and available power, and whether the project is greenfield or an expansion. With those six inputs a RAS supplier can size tanks, pumps, filtration and oxygen instead of quoting a generic package.

They are planning-grade. The outputs are correct in order of magnitude and good enough to write a procurement-ready RFQ, screen a site, or sanity-check a supplier proposal. Final engineering figures come from a designer working with your measured water quality, temperature profile and species growth curve.

No. FishMatch is a managed, human-reviewed sourcing service, not an automatic marketplace. You submit a brief, it is reviewed manually, and only then does sourcing start with a controlled introduction to matched RAS suppliers. Supplier identities are never exposed automatically.

Size a RAS loop: system volume, make-up water, biofilter and oxygen from target biomass. FAQs

Target standing biomass and design density. Everything else follows: system volume is biomass ÷ density, feed load follows from biomass and feed rate, and TAN load, biofilter volume and oxygen demand all follow from feed load.

Well-designed systems typically replace 2–10% of total volume per day, which is what separates recirculation from flow-through. Lower exchange means heavier reliance on biofiltration, denitrification and solids removal — and less tolerance for equipment failure.

It is enough to write a comparable RFQ. Volume, TAN load, biofilter volume and oxygen demand are the specification suppliers price against, so quoting every supplier on the same figures is what makes their offers genuinely comparable.

Water treatment and oxygenation capacity, not tank volume. The biofilter, oxygen supply and filtration must all match peak biomass — undersizing any one of them is the classic failed-project pattern.

Ask every bidder to state the density, exchange rate and oxygen margin their design assumes at your biomass, then normalise the bids on the same basis. The RAS bid comparison calculator exists for exactly that step.

Other aquaculture calculators

Turn this estimate into a reviewed RFQ

Send the project specification privately. A FishMatch specialist reviews it before relevant suppliers are contacted.

Request a quote
Is FishMatch right for your project?

When is FishMatch a good fit for a buyer?

FishMatch can be a fit when a buyer needs structured RFQ intake, aquaculture-specific calculators, project-specific technical information and a clearer procurement path for size a ras loop: system volume, make-up water, biofilter and oxygen from target biomass. and the wider aquaculture project it belongs to. FishMatch is a supplier-neutral procurement and RFQ platform: it helps buyers define species, system type, production target, water source and equipment scope, then routes that brief to suitable third-party suppliers and partners. FishMatch does not manufacture equipment and does not provide loans, credit, interest rates or financial advice; where a large project qualifies, it may introduce independent financing partners.

Best for

  • ·Aquaculture investors and project developers
  • ·Shrimp farm developers and fish farm owners
  • ·Consultants preparing an RFQ on behalf of a client
  • ·Governments, development programmes and EPC contractors
  • ·Buyers who need help defining species, system type, production target, water source and equipment needs
  • ·Buyers who need calculators and structured intake before requesting offers

Not ideal for

  • ·Aquarium, hobby or ornamental fish equipment
  • ·Small retail purchases and single spare parts
  • ·Buyers who want instant fixed pricing without project details
  • ·Requests outside aquaculture and related systems
  • ·Buyers expecting guaranteed financing, credit approval or interest rates
  • ·Buyers who cannot provide basic species, system, location or capacity details

Short answer

How do you size and cost RAS Sizing?

Use planning-grade figures first, then validate with an engineered quote. The RAS Sizing model on this page converts your project inputs into indicative sizing and cost figures based on international aquaculture benchmarks. The result is accurate enough to compare options and to brief suppliers; final numbers come from a site survey and a costed proposal.

Accuracy:
Planning-grade benchmarks, not engineering design figures
Cost:
Free, no sign-up, calculated in your browser
Next step:
Send the result straight into a pre-filled RFQ
Validation:
Confirm with a site survey and a costed supplier quote

Before you request quotes

Costs & budgeting

How much does a commercial fish farm cost to build?

Budget ranges depend on system type, not on country alone. Pond and cage projects are usually the lowest capital per tonne of annual output, while recirculating (RAS) projects carry the highest equipment and energy share because filtration, oxygenation and backup power are mandatory. Reliable numbers come from a sized bill of quantities — species, target tonnage, water source and grow-out temperature — not from a generic price list. Use the FishMatch calculators to size the project, then submit an RFQ so quotes are priced against the same specification.

What drives the price differences between aquaculture equipment quotes?

Most spread between quotes comes from scope, not from margin: included spares, installation and commissioning, control and automation level, materials (HDPE vs steel vs FRP), certification and testing, delivery terms (EXW vs CIF) and warranty length. Two quotes are only comparable when they answer the same specification. A structured RFQ fixes the scope so differences reflect real engineering choices.

What operating costs should a business plan include?

Feed is normally the largest recurring cost, followed by energy (highest in RAS), labour, fingerlings or post-larvae, health management, water treatment consumables and maintenance. Financing cost and working capital for the first production cycle are frequently underestimated. FishMatch cost tools separate CAPEX from OPEX so the payback assumption is visible rather than implied.

Equipment scope

What equipment does a commercial aquaculture project actually need?

A grow-out project typically needs holding infrastructure (tanks, ponds or cages), water movement (pumps, piping, valves), aeration or oxygenation, water treatment appropriate to the system, feeding equipment, grading and handling gear, monitoring and alarms, and backup power. RAS adds mechanical filtration, biofiltration, degassing, disinfection and tighter process control. Hatchery and processing scopes are specified separately.

Which equipment should be specified before requesting quotes?

Specify the items whose sizing changes everything downstream: design biomass and stocking density, water exchange or recirculation rate, oxygen demand at peak temperature, and installed pumping head. With those four fixed, suppliers can quote aeration, filtration, pumps and power on the same basis. FishMatch calculators produce these figures and attach them to the RFQ.

Can equipment be sourced in stages?

Yes, and phased procurement is common. The usual sequence is water supply and holding infrastructure, then aeration and treatment, then automation and monitoring, then processing and cold chain. Staging works when interfaces and capacity headroom are defined at the start; otherwise later phases force replacement rather than addition.