Short answer

Which aquaculture equipment suppliers meet Norway's NS 9415 and fish-welfare standards?

Norway's salmon sector runs on NS 9415-certified sea cages, heavy-duty moorings, large post-smolt RAS, feed barges and Mattilsynet-aligned delousing and welfare systems. FishMatch Group shortlists suppliers that already deliver to Nordic cold-water sites and can document compliance, commissioning support and spare-part response inside Norway — then runs one confidential RFQ across them.

You send a single brief, we approach project-matched manufacturers and distributors, and you receive comparable quotations on identical scope once suppliers respond. Supplier identities remain confidential throughout the process, and buyers pay no platform fee.

Coverage:
Norway, including Troms, Trøndelag, Vestland, Rogaland and Oslofjord
Verified categories:
NS 9415 cages, post-smolt RAS, feed barges, delousing, monitoring
Typical timing:
Varies by scope, country and supplier interest
Cost to buyer:
Free — suppliers cover the sourcing fee
Compliance focus:
NS 9415, Mattilsynet, CE/EEA, fish welfare and escape prevention
Limitations:
Commercial projects only; indicative budgets are not engineered quotes

Norway aquaculture production: evidence for your project brief

FAO FishStat, release 2025.1.0; reporting year 2023. National historical production is context, not supplier availability, site suitability, project yield or a cost estimate.

The published explorer records approximately 1,649,983 tonnes for Norway in 2023, across reported aquaculture groups, including aquatic plants where recorded.

Five-year comparison: 1,355,117 tonnes in 2018 versus 1,649,983 tonnes in 2023. These are exact reporting-year endpoints; missing years are not interpolated.

Largest reported groups in Norway, 2023
FAO species groupRounded tonnesSource flags
Salmons, trouts, smelts1,633,935No flag
Cods, hakes, haddocks11,389No flag
Mussels2,199No flag
Flounders, halibuts, soles1,903No flag

Flags from FAO: E = FAO estimate, I = imputed, N = not significant (<0.5 t), B = series break. No flag = official value. Totals sum the explorer’s rounded group quantities; small rounding differences from the underlying FAO file are possible.

What this changes in a Norway RFQ

Confirm your actual species and life stage rather than using a national group as a design target. Salmons, trouts, smelts is the largest reported group here, but this does not establish that your species, system or equipment is locally available. Supply water analysis, peak biomass and feed load, power reliability, site survey and written installation responsibilities for project-specific review.

FAO. Fishery and Aquaculture Statistics. Global aquaculture production (release 2025.1.0). FishStat. Rome. Licence: CC BY 4.0. Source file dated 2025-03-27; retrieved 2026-10-17 13:31 UTC.

Norway market focus

Aquaculture in Norway: what buyers are sourcing.

Norway produced more than 1.5 million tonnes of Atlantic salmon in 2024 and is now the world's largest supplier of high-value smolt and post-smolt. The market is shifting from volume-only sea cages toward smarter, regulation-driven capital deployment: producers are buying larger post-smolt RAS systems to shorten sea time, replacing older cages with NS 9415-certified units for exposed fjord and offshore sites, and investing in welfare-compliant delousing and wellboat upgrades to stay inside the Traffic Light System.

Buyers we work with in Troms, Trøndelag, Vestland and Rogaland are most often sourcing NS 9415 sea cages and moorings, land-based post-smolt RAS, feed barges, thermal/freshwater delousing, wellboat process packages and live-fish handling systems, plus the oxygenation, monitoring and cold-chain equipment that sits behind them. FishMatch runs one confidential RFQ across Nordic and international suppliers so you compare like-for-like on identical scope and documentation .

salmontrout

Norway is the world's largest Atlantic salmon producer, and its buyers are among the most technically demanding anywhere: NS 9415-compliant sea-cage systems, large post-smolt RAS, and equipment specified for cold, exposed, high-energy sites. Sourcing here is less about finding a supplier and more about proving compliance, documentation and service response before the contract.

Species focus and the systems buyers specify

SpeciesSystemsSourcing notes
Atlantic salmon — grow-outNS 9415 sea cages, heavy moorings, feed barges, sensor and camera systemsCircular plastic and steel collars (90–160 m), site-specific mooring to load classes B–F+, net handling, delousing, biomass cameras and lice counters. NS 9415 certification and a documented site-specific mooring analysis are mandatory. Offshore and exposed licences are driving heavier grid moorings and semi-closed containment systems.
Atlantic salmon — smolt & post-smoltLand-based RAS with full redundancyFastest-growing capital segment: large RAS halls producing 100–1,000 g post-smolt to shorten sea time under the Traffic Light System. Buyers specify drum filters (40–100 µm), MBBR biofilters, CO₂ stripping, oxygen cones or low-head oxygenators, heat recovery, N+1 pumping and 24–48 hour emergency oxygen response. Design density is typically 60–80 kg/m³ and energy target 3.5–6.0 kWh/kg produced.
Rainbow troutSea cages and freshwater flow-throughSmaller but established segment, especially in fjord and lake sites. Equipment set is similar to salmon at lower scale: cages and nets, aeration/oxygenation, feeding systems and handling equipment, with NS 9415 and Mattilsynet welfare requirements applied proportionally.
Cleaner fish (lumpfish, wrasse)Land-based hatchery / small-tank RASSpecialist hatchery, live-feed, rotifer and small-tank RAS equipment supporting sea-lice management. Buyers prioritize biosecurity, disinfection routines and references from cleaner-fish hatcheries rather than generic RAS.
Cod (emerging restocking)Hatchery and sea-cage trialsNiche but re-emerging: land-based juvenile production and trial sea-cage sites need robust RAS weaning systems, predator-proof nets and cold-water handling systems.
Shellfish / other marine speciesLong-line, rope and bottom cultureMinor in Norway compared to salmonids, but scallop and blue mussel culture needs specialized long-line, raft, spat collection and depuration equipment.

What is driving equipment demand

  • Post-smolt strategy: producers move more of the cycle on land, driving large land-based RAS equipment packages.
  • Sea-lice regulation pushes investment in delousing, shielding skirts, submerged and semi-closed systems.
  • Exposed and offshore licences require heavier moorings, stronger cages and remote monitoring.
  • Energy cost and electrification drive interest in efficient pumping, blowers and heat recovery.
  • Fish welfare and traceability regulation raise the bar on monitoring, logging and documentation.

Permits, standards and documentation for Norway: Norway aquaculture compliance guide.

Regulatory requirements

What salmon farming equipment must satisfy in Norway

  • NS 9415 — Norwegian standard for marine fish farm installations: cages, nets and moorings must be certified with site-specific analysis and documentation.
  • Traffic Light System — production capacity is regulated per zone based on sea-lice and environmental performance; equipment choices affect compliance outcomes.
  • Mattilsynet (Norwegian Food Safety Authority) — fish health, welfare and biosecurity requirements shape handling, transport and delousing equipment design.
  • Fish welfare and escape prevention — submerged and semi-closed containment systems, shielding skirts and robust net solutions are increasingly required.
  • Live-fish transport — wellboats moving fish in or out of restricted zones must use closed transport with treated and disinfected intake and discharge water, with Mattilsynet approval and logged treatment documentation.
  • CE marking and EEA electrical compliance — machinery and wet-area electrical systems need documented conformity to Norwegian and EEA rules.
Compliance checklist

NS 9415 compliance checklist for Norwegian sea-cage equipment

NS 9415 is the Norwegian standard for marine fish farm installations. It is not a single certificate — it is a chain of site data, dimensioning, product certificates and as-built documentation that must line up before a site is approved. Use this checklist as an RFQ annex so every quoted supplier prices the same documentation scope.

  1. 1. Site survey (lokalitetsundersøkelse)

    Requirement: Measured current, wave, wind, depth and bottom conditions for the specific licence site, valid and not older than the standard's accepted interval.

    Evidence to request: Site survey report from an accredited body, with the design current and Hs values quoted in the equipment dimensioning.

  2. 2. Mooring analysis and mooring certificate

    Requirement: Site-specific mooring dimensioning against the survey loads, including anchor type, chain and rope dimensions, safety factors and grid geometry.

    Evidence to request: Mooring analysis report plus product certificates for anchors, chain, shackles, ropes and buoys.

  3. 3. Cage collar and net-cage product certificate

    Requirement: Certified plastic or steel collar and net cage dimensioned for the site's load class, with documented residual strength and inspection intervals.

    Evidence to request: Product certificate (produktsertifikat) per component and a system certificate for the assembled installation.

  4. 4. Netting, ropes and escape prevention

    Requirement: Net material, mesh, breaking strength, weight system and bird/predator protection specified against the load class; sinker tube or weight configuration documented.

    Evidence to request: Net certificate with test reports, plus a documented escape-prevention design for the fish size range.

  5. 5. Feed barge and floating structures

    Requirement: Stability, mooring interface, fire safety, spill containment and electrical zoning documented for the barge and any service floats.

    Evidence to request: Class or accredited body approval, stability booklet and mooring interface calculation.

  6. 6. Machinery and CE conformity

    Requirement: Delousing units, feed blowers, net cleaners, cranes and winches CE-marked under the Machinery Directive with EEA-valid conformity.

    Evidence to request: Declaration of conformity, technical file availability statement, and Norwegian or bilingual O&M manuals.

  7. 7. Electrical and wet-area installation

    Requirement: Marine and wet-area electrical installation to Norwegian/EEA rules, IP ratings and earthing documented; hazardous zones assessed where relevant.

    Evidence to request: Electrical documentation package and installation certificate from a Norwegian-registered installer.

  8. 8. Fish welfare and handling equipment

    Requirement: Crowding, pumping, sorting and delousing equipment designed to Mattilsynet welfare expectations, with documented flow rates and mortality-risk assessment.

    Evidence to request: Welfare assessment or supplier documentation of tested throughput and fish-friendly design.

  9. 9. Installation, inspection and as-built dossier

    Requirement: Installation by qualified personnel, first inspection, and a complete as-built documentation set kept at the site.

    Evidence to request: Installation report, main-component list (hovedkomponentliste) and inspection plan with intervals.

  10. 10. Service response and spares in Norway

    Requirement: Guaranteed response time, Norwegian-language support and stocked spares for critical components.

    Evidence to request: Written service-level commitment in the quotation, plus named Norway-based service partner and spares list.

Standards and interpretations change — confirm the current scope with an accredited body before contracting.

NS 9415 & Mattilsynet

Norway compliance FAQ

Answers to the buyer questions that come up most often around NS 9415 certification, load classes, Mattilsynet welfare requirements and the documentation chain.

NS 9415 is the Norwegian standard for marine fish farm installations. It covers dimensioning, certification, installation and documentation of sea cages, nets and moorings. For buyers, it means every cage and mooring system must be matched to a site-specific load class and supplied with product certificates and as-built documentation — otherwise the installation cannot be legally approved.

Cages, nets, moorings, anchors, chains, ropes, buoys, feed barges and floating structures must be dimensioned and certified under NS 9415 for the specific site load class. Delousing, handling and wellboat equipment must also be documented, but their welfare and safety evidence is governed by Mattilsynet and EEA machinery rules rather than NS 9415 itself.

Mattilsynet, the Norwegian Food Safety Authority, sets requirements for fish health, welfare and biosecurity. Equipment for handling, transport, delousing and slaughter must be designed to minimize stress, injury and mortality, and must be supported by welfare documentation and operational procedures. This affects the specification of pumps, crowding systems, delousers and wellboat water treatment.

NS 9415 classifies sites from sheltered (A) to highly exposed (F+) based on measured current, wave height and wind. The load class determines the collar circumference, net depth, netting strength, mooring layout and safety factors that must be quoted. A supplier must state the certified load class for every cage and net component, and a site-specific mooring analysis must back it up.

A product certificate confirms that an individual component — a collar, net, anchor, chain or rope — meets NS 9415 for a given load class. A system certificate confirms that the assembled cage, net and mooring system is correctly dimensioned and documented for the specific site. Buyers need both, plus the site-specific mooring analysis, to satisfy Norwegian authorities.

Land-based RAS and post-smolt facilities are not covered by NS 9415, which is a marine cage standard. They are governed by local building and environmental permits, the Norwegian Food Safety Authority for fish health and welfare, and EEA machinery and electrical rules. Mattilsynet expectations still shape equipment design, especially for gentle handling, disinfection and biosecurity.

Require: the site survey, site-specific mooring analysis, NS 9415 product certificates for all components, system certificate for the assembled installation, net test reports, escape-prevention design, feed-barge stability and mooring interface, CE declarations for machinery, electrical installation certificates, and the as-built dossier with inspection intervals.

Mattilsynet welfare rules require that delousing and transport systems minimize stress, crowding time and injury. This means mechanical delousers, freshwater and thermal treatments, wellboat pumping and transfer systems must be sized for the fish size and density, and suppliers must provide throughput and mortality-risk data. Closed wellboat transport with treated water is often required for disease-area movements.

Yes, but they must either hold NS 9415 product certificates for the components they sell, partner with a Norwegian body that performs the site-specific analysis and certification, or deliver machinery that can be integrated into a certified system by a Norwegian installer. FishMatch runs Nordic and international suppliers in the same RFQ and checks that each bid includes the required documentation chain.

Compliance is shared. The buyer typically commissions the site survey because it belongs to the licence. The supplier is responsible for product certificates and often the site-specific mooring analysis. Installation and final inspection must be performed by accredited parties. The RFQ must clearly state which party delivers each deliverable so bids are comparable.
Cost benchmarks

Post-smolt RAS cost benchmarks in Norway

Indicative planning benchmarks for land-based post-smolt facilities in Norway (typically 100–1,000 g fish, freshwater or brackish RAS with full redundancy). Figures are per kg of annual production capacity unless stated, based on European supplier quotations and Norwegian build conditions. Use them to sanity-check a budget before quotes arrive — not as a quotation.

Cost itemIndicative benchmarkWhat drives it
Total delivered project CAPEXNOK 220–380 per kg annual capacity (≈ USD 20–35/kg)Turnkey, including building, process equipment, water intake/discharge and commissioning. Below NOK 200/kg usually means scope has been left out.
RAS process equipment onlyNOK 90–160 per kg annual capacity (≈ USD 8–15/kg)Drum filters, MBBR/moving-bed biofilters, degassers, CO₂ stripping, oxygen cones, pumps, UV/ozone, instrumentation and control.
Building and civil works35–50% of total CAPEXNorwegian construction cost, insulation, rock excavation and concrete tanks dominate; site geology moves this line more than equipment choice.
Tank volume required≈ 1 m³ per 55–70 kg standing biomassPost-smolt density is commonly designed at 55–70 kg/m³; higher densities raise oxygen, degassing and redundancy cost disproportionately.
Electricity consumption3.5–6.0 kWh per kg producedPumping, oxygenation, degassing and heating. Heat recovery and low-head pumping are the two biggest levers at Norwegian power prices.
Liquid oxygen0.5–0.9 kg O₂ per kg feedCompare liquid oxygen supply against on-site generation once consumption passes roughly 300–400 tonnes per year.
Make-up water150–400 litres per kg producedDepends on nitrate strategy and whether the facility runs freshwater or brackish; discharge permit conditions set the floor.
Total production cost (post-smolt)NOK 22–38 per kg of post-smolt producedFeed, energy, oxygen, labour, maintenance and smolt input, excluding capital cost and financing.
Long-lead engineered items16–40 weeksFilters, biofilter media, oxygen systems and switchgear should be released before the building contract is finalised.

Benchmarks are indicative planning ranges for budgeting only and will move with site geology, power price, water source, permit conditions and steel/currency movements. FishMatch Group is supplier-neutral and does not guarantee pricing — request matched quotations to confirm.

Startup sequence

How to start a fish or shrimp farm in Norway

  1. 1. Secure the licence and site (Akvakulturtillatelse)

    Norwegian county authorities award the site in coordination with Mattilsynet, the Directorate of Fisheries and the Norwegian Environment Agency. Nothing about the equipment specification is final until the licence, MAB (maximum allowed biomass) and production-area rules for the site are confirmed.

  2. 2. Commission the site survey (lokalitetsundersøkelse)

    An accredited body measures design current, wave height, depth and bottom conditions. This survey sets the NS 9415 load class and therefore which cage, net and mooring products you are allowed to buy — run it before freezing the specification, not after.

  3. 3. Fix the technical scope and load class

    Translate the survey into cage circumference, net dimensioning, mooring layout and feed-barge interface. For land-based post-smolt, fix capacity, target smolt size, tank volume and density, water exchange, guaranteed kWh/kg and oxygen consumption before any bidder prices the package.

  4. 4. Run one RFQ on identical scope

    Issue the same specification and NS 9415 documentation list to Nordic and international suppliers in the same round so degassing, backup oxygen, commissioning and spares are inside every price rather than a later variation order.

  5. 5. Line up financing against the bankable spec

    Equipment finance, leasing and project finance partners want the licence, site survey, EPC or supply contract and specification in one pack. Prepare it alongside the RFQ so approval does not sit behind the delivery schedule.

  6. 6. Plan installation around weather and vessels

    Mooring installation, cage deployment and accredited inspection all depend on weather windows and vessel availability, especially in Troms and Finnmark. Book service vessels and inspection early — schedule risk in Norway is rarely manufacturing lead time.

  7. 7. Commission, verify and take over the documentation

    Close out with as-built dossier, product certificates, inspection intervals, electrical certificates, CE declarations, spare-parts kit and a named Norwegian service partner with an agreed response time before final payment.

Regulatory requirements change — confirm current scope with the relevant authorities or a local agent before fixing your schedule.

Ports & logistics

Getting equipment into Norway

Norway is a high-cost, well-connected market. Most equipment arrives via continental European road freight or containers through Oslo and the west-coast ports, then moves by road and coastal vessel to the fjord sites. Site access, crane availability and weather windows usually govern the schedule more than shipping does.

Oslo

Main container gateway

Best-connected for containerised equipment from Asia; onward road distribution nationwide.

Bergen / Ågotnes

West-coast aquaculture hub

Close to the main salmon-farming region; service base for cages, moorings and vessels.

Trondheim

Mid-Norway hub

Serves the Trøndelag farming cluster and several large land-based projects.

Bodø / Tromsø

Northern hub

Serves northern Norway; longer inland transfers and tighter weather windows.

Road from EU

Continental road freight

Common for European-built RAS and processing equipment — faster and simpler than sea freight.

Regional clusters

Where Norwegian aquaculture equipment is needed

Troms & Finnmark

Highest-volume salmon region

Northern Norway dominates volume; exposed sites, long seasons and strong land-based RAS investment.

Trøndelag

Mid-Norway farming cluster

Large post-smolt RAS projects and established service infrastructure; Trondheim is the main logistics hub.

Vestland (Bergen / Ågotnes)

West-coast aquaculture hub

Close to fjord farms; service base for cages, moorings, vessels and field engineering.

Rogaland & Agder

Southern service corridor

Processing and equipment-service clusters, plus shorter road links to the EU for continental suppliers.

Oslofjord / Eastern Norway

Container gateway & inland support

Main container entry point and access to European road freight and inland service providers.

Verified categories

Verified equipment categories we source for Norway

Every supplier we shortlist for a Norwegian project is screened on the same four points before quoting: proven delivery to Nordic cold-water sites, the certification chain the category requires, Norway-based or Nordic service response, and documentation in Norwegian or bilingual form. These are the categories we run RFQs for most often.

Sea cages, nets and moorings

Plastic and steel collars (typically 90–160 m circumference), nets, sinker tubes, anchors, chain and grid moorings for exposed and high-energy sites. NS 9415 load classes B–F+ depending on current and wave exposure.

How we vet: NS 9415 product and system certificates, site-specific mooring analysis capability, and documented load-class references in Norwegian waters.

Sea cages, nets and moorings suppliers

Post-smolt and smolt RAS packages

Drum filters (40–100 µm), MBBR biofilters, degassers, CO₂ stripping, oxygen cones or low-head oxygenators, low-head pumping, UV/ozone, instrumentation and control. Sized from peak daily feed load, not tank count.

How we vet: Delivered Nordic RAS references at comparable biomass, redundancy philosophy on paper, and commissioning plus biofilter start-up included in scope.

Post-smolt and smolt RAS packages suppliers

Water treatment and filtration

Mechanical filtration, biofiltration media, intake screening, discharge TSS control and disinfection against Norwegian permit conditions. Freshwater and brackish/seawater variants.

How we vet: Performance guarantees tied to measured parameters (TAN, CO₂, TSS, nitrate), EEA conformity, and spare media and cartridge availability from a Nordic stock.

Water treatment and filtration suppliers

Oxygenation and aeration

Oxygen cones, low-head oxygenators, liquid oxygen systems, on-site PSA or LOX generation, emergency oxygen backup and diffusion. Typical duty: 0.4–0.5 kg O₂ per kg feed for salmonids.

How we vet: Documented transfer efficiency at design temperature, sizing against your kg O₂ per kg feed load, and a written emergency-supply arrangement.

Oxygenation and aeration suppliers

Feed barges and feeding systems

Feed barges (100–1,500+ tonnes silo capacity), central feeding, blowers, pipework, feed cameras and control software. Stability and mooring-interface documentation required.

How we vet: Yard slot transparency, stability and mooring-interface documentation, and integration with the farm's existing control platform.

Delousing and fish welfare handling

Freshwater and thermal treatment systems, mechanical delousers, crowding and pumping, lice skirts and snorkel designs, semi-closed containment systems.

How we vet: Mattilsynet-aligned welfare documentation, tested throughput at your fish size, and mortality-risk assessment supplied with the quotation.

Wellboat systems and live-fish handling

Wellboat process packages and retrofits: closed/open transport modes, RSW chilling, oxygenation and CO₂ degassing, water treatment and UV disinfection of transport water, fish pumps, counters and vacuum/gentle-handling transfer, plus onboard freshwater and thermal delousing modules.

How we vet: Mattilsynet transport approval and disinfection documentation, verified pumping capacity in tonnes/hour at your fish size, welfare and mortality data from Norwegian voyages, and a Norway-based service and spares commitment.

Monitoring, sensors and biomass systems

Biomass cameras, lice counters, oxygen and temperature probes, feeding cameras, environmental sensors and farm-management software with open data interfaces.

How we vet: Open data interfaces, calibration and service intervals, and proven operation at Norwegian light and temperature conditions.

Monitoring, sensors and biomass systems suppliers

Processing, grading and cold chain

Grading, stunning and bleeding lines, RSW tanks, ice systems, chilling and packing for salmon and trout. EU/EEA hygiene design compliance.

How we vet: EU/EEA hygiene design compliance, food-contact material certificates, and a Nordic service engineer network.

Hatchery and cleaner-fish equipment

Incubation, small-tank RAS, live-feed systems and start-feeding equipment for smolt and lumpfish/wrasse production. Biosecurity-focused design.

How we vet: Biosecurity design, disinfection routines and references in cleaner-fish or smolt hatcheries specifically, not generic RAS.

Lead times

Indicative delivery lead times

Standard cages and nets8–20 weeks
Longer in the spring pre-stocking peak; NS 9415 documentation must accompany delivery.
Mooring systems10–24 weeks
Site-specific design and analysis add engineering time before manufacture.
RAS process equipment (filters, biofilters, oxygenation)16–40 weeks
Large post-smolt packages are engineered to order; long-lead items should be released early.
Feed barges9–18 months
Effectively a shipbuilding project; slot booking, not just ordering.
Sensors, cameras and monitoring4–12 weeks
Shorter, but integration and commissioning need scheduling with the farm's systems.

Planning benchmarks only — confirm against supplier quotations for your scope.

Documentation & compliance

What buyers in Norway must document

NS 9415 certification
Norwegian standard for marine fish farm installations — cages, nets and moorings must be certified and site-specific analysis documented.
CE marking and Machinery Directive
Required on machinery placed in the EEA market; declaration of conformity and technical file must be available.
Norwegian Food Safety Authority (Mattilsynet) requirements
Fish health, welfare and biosecurity provisions affect equipment design, especially handling, transport and delousing systems.
Electrical and ATEX compliance
Marine and wet-area installations require documented electrical compliance to Norwegian and EEA rules.
Documentation language
Manuals, HSE documentation and O&M instructions are commonly requested in Norwegian or bilingual — write it into the RFQ.
Service response commitments
Norwegian buyers routinely score suppliers on guaranteed response time and Norway-based service capacity, not just price.
Landed-cost drivers

What moves the delivered cost in Norway

  • Norway is a high labour-cost market; installation and commissioning scope is a large share of delivered cost.
  • Certification, documentation and third-party verification are a real budget line, not overhead.
  • Service response and local spares presence often outweigh unit price in supplier evaluation.
  • Weather windows and vessel availability drive schedule risk more than manufacturing lead time.
  • EEA-built equipment avoids import duty and shortens the documentation route versus Asian supply.
What buyers in Norway look for

Aquaculture supplies and supply companies for Norwegian fish farms

In Norway, people search for aquaculture supplies and supply companies serving salmon farms: cage nets and moorings certified to NS 9415, feed barges, camera and feeding control, delousing and net cleaning equipment, and post-smolt RAS on land. Most buyers compare an established Nordic supplier with an alternative offer on the same scope, delivery date and service contract.

  • Cage, mooring and net packages documented to NS 9415
  • Post-smolt RAS, oxygen and water treatment for land sites
  • Compare supply companies on service response along the coast

Norway market facts

Production
1.479 million t of salmon and trout harvested in 2023; exports NOK 122.4 bn · source
Main farmed species
Atlantic salmon, rainbow trout, shellfish · source
Import duty
Manufactured goods mostly duty-free (non-farm average MFN ~1.1%); confirm the exact line with Norwegian Customs · source
VAT on imports
25% standard rate
Market rules
Mattilsynet approves facilities; the Directorate of Fisheries runs site licences and the traffic-light production-area system · source

Typical equipment prices for Norway projects

EquipmentPublic price rangeSource
HDPE floating fish cage (small to mid)Common in NorwayUSD 2,000 – 10,000 per cageManufacturer price listings
Commercial RAS, equipment + installationCommon in NorwayUSD 9,000 – 25,000 per tonne of yearly capacityRAStech capital cost study
PSA oxygen generator for fish farmsCommon in NorwayUSD 5,000 – 40,000 by capacityManufacturer price listings
Drum filter, 30–100 m³/hCommon in NorwayUSD 1,250 – 3,540Public drum filter price list
Paddlewheel aerator, 2 HPUSD 300 – 1,250 per unitFactory listing (USD 299) to US retail (USD 1,250)
Automatic pond feeder (40–120 kg hopper)USD 85 – 900 per unitManufacturer price listings

Planning estimate only: public list prices, before shipping to Norway, import duty, installation and local taxes. Your quote depends on capacity and scope.

Project examples

Recent sourcing briefs from Norway

Real requests the FishMatch desk has worked on with buyers in Norway — anonymized to protect buyer and supplier confidentiality. Each one started as a rough idea and became a structured RFQ that project-matched suppliers could price on identical scope.

Rogaland

Post-smolt RAS expansion to 600 g

≈1,500 t/year post-smolt capacity

Full recirculation package: drum filtration, CO₂ degassing, oxygen cones, moving-bed biofilter, UV, backup oxygen and generator, with tank hydraulics sized for 600 g smolt delivery.

How the desk handled it: The brief arrived as a single 'RAS system' line. The desk split it into process, electrical and life-support-backup scopes so bidders priced the same package, then ran the RFQ to suppliers with documented Norwegian post-smolt references.

Trøndelag

Feed barge replacement with NS 9415 documentation

≈450 t silo capacity feed barge

Feed barge with central feeding system, blowers and pipework, stability booklet, mooring-interface calculation, CE machinery declarations and Norwegian electrical certificates.

How the desk handled it: The desk attached the site's mooring analysis to the RFQ so every yard priced the same interface and documentation load class — removing the most common cause of non-comparable barge quotes.

Møre og Romsdal

Non-medicinal delousing package

Six-pen site, ≈3,000 t standing biomass

Thermal/mechanical delousing system with wellboat interface, lice-count monitoring integration and service-level agreement for the production cycle.

How the desk handled it: Supplier shortlist was filtered on verified welfare and fish-handling documentation before pricing, so the comparison covered treatment performance and service response — not just machine cost.

Figures are indicative planning benchmarks, not engineered quotations. Supplier identities remain confidential throughout the process.

Sourcing equipment in Norway — how it works.

  1. 01

    1. You submit the project request

    Send one structured brief: species, target tonnage, system type (RAS, ponds, cages, hatchery), country, site conditions, budget range and timeline. It takes a few minutes and is free.

  2. 02

    2. FishMatch reviews and prepares the brief

    the FishMatch project team review the request personally. If the need, scale, budget or technical direction is not yet clear, we work with you to sharpen it before any supplier sees it.

  3. 03

    3. FishMatch searches for suitable suppliers

    Only once the brief is clear do we search our matched supplier and manufacturer network for companies whose equipment, track record and service coverage actually fit the project.

  4. 04

    4. The FishMatch team continues the process with you

    You receive comparable quotations and guidance on the trade-offs. The FishMatch team introduces relevant suppliers directly only when you decide to engage — there is no automatic matching and no open marketplace.

FishMatch Group is not a manufacturer, farm operator, lender or engineering contractor, and does not guarantee any supplier. Supplier identities stay confidential until you choose to engage. The supplier directory on this page is for research and discovery — buyer follow-up and supplier selection are handled personally by the FishMatch team.

Equipment we source in Norway

Land-based salmon

Post-smolt & smolt RAS equipment sourcing

Filtration, degassing, oxygenation, water treatment and controls sized from daily feed load — specs, capacity bands, cost drivers and the RFQ fields suppliers need.

Financing in Norway

Need financing for your project in Norway?

Qualified projects in Norway may be introduced to independent third-party equipment, turnkey or expansion financing providers. Approval and terms are set solely by the provider.

Check financing
Buyer guide

Fish Farming Suppliers in Norway: Aquaculture Procurement

Local and international suppliers can both serve projects in Norway. Before comparing them, put every quote on the same basis.

  1. 1.Write one specification first

    Species, target tonnes per year, system type, site, water source and budget. Quotes built on the same brief can be compared line by line; quotes built on different assumptions cannot.

  2. 2.Ask for the same delivery terms

    Request every price on the same Incoterms® 2020 rule (for example FOB or CIF, named port). Mixed terms hide freight, insurance and duty differences (ICC).

  3. 3.Separate equipment from design and installation

    Ask suppliers to price equipment, engineering, installation supervision, commissioning and training as separate lines, so missing scope is visible.

  4. 4.Check the technical basis

    For RAS, ask how flow, oxygen and biofilter capacity were sized from the feed load — the method in Timmons & Ebeling is a common reference.

  5. 5.Confirm certification needs early

    If your buyers require ASC or BAP, tell suppliers before design and check the applicable standard. FAO's certification guidelines provide a broader reference for environmental, social, food-safety and animal-health criteria; they do not certify a supplier or a project.

  6. 6.Compare total cost, not unit price

    Include spares, warranty terms, currency, payment milestones and lead time. The lowest equipment price is not always the lowest project cost.

How FishMatch Group handles aquaculture procurement

A specialist reviews your brief, asks for anything missing, then contacts relevant suppliers privately. Available proposals are organised in one comparison, line by line, with differences and exclusions identified. FishMatch Group is supplier-neutral: it does not manufacture equipment, build or operate farms, or lend. Supplier names, websites and contact details stay confidential. We do not guarantee a number of proposals, the lowest price or financing approval.

Open the RFQ form →

Planning a shrimp farm? Get a free cost estimate from your pond size, stocking density and harvest goals

Sources

Structured intake

Full RFQ intake for your aquaculture project

Human-reviewed infrastructure RFQs start at USD 250,000. Buyers pay nothing; sourcing is supplier-funded. Define species, capacity, system, measured water conditions, equipment scope, standards, destination, timing and budget. Supplier identities remain confidential. Smaller requests are saved separately and directed to free planning tools.

Your details are never published and never shared with a supplier under your name without approval.

FishMatch Group and the other Global B2B Group platforms are committed to conducting their own activities in accordance with applicable laws and regulations. FishMatch facilitates sourcing and RFQs; it does not manufacture, process, export or sell the listed products and does not grant regulatory approval. Requirements differ by product and by origin, destination and transit country. As buyer or importer, you remain responsible for your own import permissions, local requirements and due diligence. This notice does not change anyone's legal duties and is not legal advice. Regulation & responsibilities

Supplier and manufacturer listings are provided for research, transparency and discovery only. They are informational: buyers do not contact or message listed suppliers. Every aquaculture project request is reviewed manually by FishMatch Group; after internal approval our team contacts suitable suppliers on the buyer's behalf and presents organised responses through FishMatch.

Step 1 of 5

1. Contact

1. Contact

Your contact details stay private and let our team clarify the project before any supplier outreach.

Privacy: We use these details to review and answer this request. They stay confidential, are shared only as described in our Privacy Policy, and are not used for marketing unless you separately opt in. We keep them while your request or account is active and for as long as legal record-keeping requires. Privacy Policy · Your rights

FAQ — Aquaculture equipment in Norway

Two segments dominate. In the sea: cages, moorings, nets, feed barges, delousing systems, cameras and biomass sensors, all specified to NS 9415 and exposed-site conditions. On land: large post-smolt RAS packages — drum filters, MBBR biofilters, degassers, CO₂ stripping, oxygen cones and full redundancy — plus cleaner-fish hatchery equipment supporting sea-lice management.

Marine fish farm installations — cages, nets and moorings — must comply with NS 9415, with site-specific analysis documented. Machinery placed in the EEA needs CE marking with a declaration of conformity and technical file. Electrical installations must meet Norwegian and EEA rules, and fish-health and welfare requirements from Mattilsynet shape handling, transport and delousing equipment design.

NS 9415 uses load classes based on measured site current, wave height and exposure. A typical Norwegian salmon site sits in load class B–F+, with collar circumference of 90–160 m, net depth of 12–25 m, and mooring systems designed to site-specific safety factors. Ask suppliers to state the certified load class for the collar and net, the breaking strength of the netting and ropes, the anchor and chain specification, and whether the mooring analysis is included or priced separately. Without this, a cage price is not comparable across bids.

Nordic post-smolt RAS must be sized for 12–16 °C design water and the higher oxygen solubility and slower nitrification kinetics that come with it. Heat pumps and heat recovery become a major OPEX line, materials may shift to coated or polymer components where brackish water is used, and biofilter maturation plans must account for a slower bacterial ramp. Cold-water duty also raises redundancy requirements: N+1 on pumps and blowers, independent life-support alarms, and emergency oxygen with 24–48 hour on-site response are standard.

Indicatively: cages and nets 8–20 weeks, mooring systems 10–24 weeks, RAS process equipment 16–40 weeks for engineered post-smolt packages, and feed barges 9–18 months. Sensors and monitoring are shorter at 4–12 weeks. Long-lead items should be released before the rest of the design is frozen.

Oslo is the main container gateway; Bergen and Ågotnes serve the west-coast farming cluster; Trondheim serves Trøndelag; Bodø and Tromsø serve the north. Much European-built equipment arrives by road from the continent instead, which is often faster and simpler than sea freight.

It depends on the package. Norwegian and Nordic suppliers bring NS 9415 experience, local service and documentation in the right language, which matters most for cages, moorings and marine systems. International suppliers are often competitive on RAS process components and general machinery. We run both routes in the same RFQ so the comparison is on identical scope.

No. FishMatch Group is an independent sourcing platform. We prepare your specification, run a confidential RFQ to project-matched suppliers serving Norway, and return comparable quotations. Buyers pay nothing and supplier identities stay confidential until you choose to engage.

As planning indications only: a complete NS 9415-certified sea-cage unit with net, mooring and handling typically runs USD 250,000–900,000 per cage depending on circumference, exposure class and site analysis; feed barges range from roughly USD 2–8 million by capacity and automation level; post-smolt RAS packages commonly land at USD 18,000–28,000 per ton of annual capacity before civil works. Norwegian installation labour, commissioning and third-party verification are a significant additional share of delivered cost, so always compare quotes on landed and installed scope, not ex-works price.

NS 9415 is the Norwegian standard for marine fish farm installations. In practice it means every cage, net and mooring must be dimensioned against a site-specific current, wave and depth analysis, supplied with certification and product documentation, and installed and inspected by accredited parties. When you request quotes, require the supplier to state which components are NS 9415 certified, who performs the site analysis, and what documentation is handed over at delivery — otherwise price comparisons are meaningless.

Producing smolt to 100–1,000 g on land shortens sea time, which lowers exposure to sea lice, reduces mortality and improves harvest predictability under the Traffic Light System capacity regime. That drives sustained demand for large drum filters, MBBR biofilters, degassers, CO₂ stripping, oxygen cones, redundant pumping and heat recovery — engineered-to-order packages with 16–40 week lead times that should be released early in the project schedule.

Production capacity in each of Norway's 13 production zones can be increased, frozen or cut based on sea-lice impact on wild salmon. Because capacity is tied to biological performance, equipment that reduces lice pressure — shielding skirts, submerged and semi-closed containment, freshwater and thermal delousing, lice counters and cameras — is treated as a capacity investment rather than a running cost, and is scored accordingly in supplier evaluations.

The main routes are non-medicinal: freshwater treatment systems, thermal and mechanical delousers on wellboats or barges, lice-skirt and snorkel cage designs, submerged feeding, and optical lice-counting with camera systems. Mattilsynet welfare rules govern handling stress, crowding and transport, so specifications must include documented welfare performance and gentle-handling design, not just throughput.

Specify the transport mode first — closed transport with water treatment is normally required in and out of areas with disease restrictions, so the package must include UV or filtration disinfection of intake and discharge water with documented log reduction. Then fix the process duty: RSW chilling capacity, oxygenation and CO₂ degassing at the planned biomass density, fish pump capacity in tonnes per hour at your average weight, counters, and gentle-handling transfer to limit scale loss. Add any onboard delousing module (freshwater or thermal) as a separate priced line with tested throughput and welfare data. Require Mattilsynet transport approval evidence, references from Norwegian voyages, and a Norway-based service and spares commitment in the quotation.

Eligible Norwegian and Nordic projects may be introduced to independent third-party equipment-finance, leasing and project-finance providers — FishMatch Group is not a lender and approval rests with the provider — typically for post-smolt RAS halls, feed barges, vessels and processing upgrades. Lenders will want a bankable specification, EPC or supply contracts, site permits and licence documentation — we can align the RFQ output to what financing partners ask for.

Nine deliverables, in order: the site survey (lokalitetsundersøkelse) with design current and wave data; the site-specific mooring analysis; product certificates for anchors, chain, shackles, ropes and buoys; collar and net-cage product certificates for the site load class; net test reports and the escape-prevention design; feed-barge stability and mooring interface approval; CE declarations of conformity for machinery; Norwegian electrical installation certificates; and the as-built dossier with inspection intervals. Attach that list to the RFQ so every supplier prices the same documentation scope.

In most Norwegian projects the operator commissions the site survey from an accredited body, because it belongs to the licence site rather than to any one supplier. The mooring analysis is normally priced by the mooring or cage supplier against that survey. Say clearly in the RFQ which side carries each item — otherwise one bidder includes the analysis, another excludes it, and the two prices are not comparable.

Allow roughly 4–8 weeks for the site survey depending on the measurement season and weather, 3–6 weeks for the mooring analysis once survey data is in hand, and product and system certificates issued alongside manufacturing. As-built documentation and accredited installation inspection close after deployment. Start the survey before you freeze the cage specification: the design current and wave height set the load class and therefore the equipment you can buy.

As planning indications only, greenfield post-smolt RAS in Norway commonly lands around NOK 200–350 per kg of annual capacity for the complete facility including civil works, with the process equipment package itself typically USD 18,000–28,000 per ton of annual capacity ex-works. Norwegian construction, installation and commissioning labour is a large share of the difference, so always compare quotes on landed and installed scope rather than ex-works price.

Planning benchmarks: roughly 3–6 kWh per kg produced for a well-designed post-smolt facility including pumping, blowers, oxygenation and heating, and around 0.6–1.0 kg of liquid oxygen per kg of feed depending on density and degassing efficiency. Design density is usually 60–80 kg/m³ in post-smolt tanks. Ask each RAS bidder to state the kWh/kg and O₂/kg their guarantee is based on — those two numbers drive OPEX more than the equipment price.

Fix the boundary before you send the RFQ: production capacity and target smolt size, tank volume and density, water exchange and make-up rate, guaranteed kWh/kg and oxygen consumption, redundancy level, control system scope, commissioning and biological start-up support, spare-parts kit, and the documentation package. Suppliers that exclude degassing, backup oxygen or commissioning always look cheaper on paper; a fixed scope sheet removes that gap.

Ask for 12–24 months on process equipment, a named Norwegian or Nordic service partner, a defined response time for critical failures — commonly 24–48 hours on site for RAS life-support — and a stocked spare-parts list for pumps, blowers, oxygen and control components. Service presence and spares stock in-country routinely outweigh unit price in Norwegian supplier evaluations, because downtime in a post-smolt hall is measured in biomass, not hours.

Submit one brief describing species, system type, target capacity, site location and target commissioning date. We prepare a comparable specification, run a confidential RFQ to manufacturers and distributors serving Norway — Nordic and international in the same round — and return matched quotations on identical scope once suppliers respond for standard packages. Buyers pay nothing and supplier identities remain confidential until you decide to engage.

Distributors and dealers active in Norway are usually regional agents for international manufacturers of aeration, pumping, feeding, filtration and monitoring equipment. FishMatch Group researches those companies from public information, then approaches the ones whose product range and service coverage match your project. We are not a distributor ourselves and do not sell equipment.

Commercial buyers in Norway normally buy directly from manufacturers or from their regional distributors rather than from retail outlets. You send one brief describing species, capacity and site conditions; we prepare a technical RFQ and run a confidential round with manufacturers, exporters and distributors that already ship to Europe.

Yes. Requests are put to manufacturers, wholesalers, exporters and turnkey contractors, selected by capability for your system type rather than by any commercial relationship. Quotes come back in a comparable format with scope, lead time and delivered cost to Norway stated the same way.

Submit one sourcing brief with your species, system and capacity. FishMatch Group matches it against manufacturers, exporters and distributors already serving Norway and Europe, then returns comparable quotes — you never have to contact suppliers one by one.

Cost depends on system type and scale rather than location: small pond or cage setups typically start in the tens of thousands of USD, while commercial RAS and turnkey farms run from several hundred thousand to multi-million USD. Landed cost in Norway also includes freight, duties, installation and commissioning — all of which are itemised in the quotes you receive.

Stock items and small equipment usually ship in 2–6 weeks. Engineered RAS, hatchery and processing lines are typically 8–20 weeks from order confirmation, plus 3–6 weeks of sea freight and customs clearance into Norway.

Yes. The manufacturers we work with export regularly to Europe and quote door-to-door where required, covering sea or air freight, customs documentation, on-site installation, commissioning and operator training in Norway.

We check company registration, export history into Europe, reference projects of comparable scale, certifications and after-sales capability before a supplier is matched to a Norway project. Supplier identities stay confidential until you decide to proceed.

There is no fixed minimum, but sourcing works best for projects above roughly USD 25,000. Smaller orders are usually matched with regional distributors serving Norway rather than factory-direct manufacturers.

Qualified projects in Norway may be eligible for equipment leasing, export credit, working capital or structured project finance from USD 250,000 upwards through our international financing partners. Financing is reviewed confidentially alongside your equipment quotes.

We prioritise suppliers with regional service coverage or a distributor presence in Europe, and spare-parts availability, warranty terms and remote support are compared as part of every quote package for Norway.

Nothing. Buyers in Norway pay no fee for sourcing, quote comparison or financing introductions — suppliers cover the fee only when a qualified opportunity is delivered.

Most complete briefs receive 2–3 matched supplier quotes once suppliers respond. Complex turnkey or RAS projects in Norway take longer because they require engineered scopes and layout drawings; timing depends on supplier response.

RAS and post-smolt systems, sea and lake cages, lined and earthen ponds, biofloc and shrimp systems, hatchery and nursery lines, feed handling, aeration and oxygenation, water treatment, cold chain and processing equipment are all sourced for projects in Norway and across Europe.

No. You submit a single brief and we run the outreach, technical clarification and price negotiation with matched manufacturers on your behalf. Supplier identities stay confidential until you decide which quote to progress for your Norway project.

Yes. Turnkey scopes covering process design, civil interface, equipment supply, installation, commissioning and operator training are quoted by EPC partners with delivery experience in Europe, so the Norway package arrives as one comparable price rather than a dozen separate line items.

Species, target annual tonnage, site water source and quality, available land or sea area, power availability and a target start date are enough to begin. Site drawings, permits and water analyses for Norway sharpen the engineered scope but are not required for the first round of quotes.

We match suppliers whose equipment, certification and documentation meet the standards enforced in Norway and Europe, and quotes include the technical files, CE or equivalent conformity documents and effluent or biosecurity specifications your permitting process is likely to request.

Every quote is returned in a comparable format: equipment scope, capacity assumptions, energy and labour requirements, Incoterm and freight to Norway, installation, warranty, spare parts and payment terms — so you compare total delivered cost of ownership instead of headline equipment price.

Norwegian salmon sourcing — where buyers go next

Norway projects rarely stop at one category. These are the equipment, hatchery, cost and peer-market pages Norwegian and Norway-facing buyers open after this one.

Explore aquaculture and RAS suppliers here for research and market discovery, or start with your project requirements so FishMatch can help structure the RFQ and identify relevant system providers for that specific production plan.

Directory — research

Browse categories, countries and technology types to understand the market and which system types exist. Nothing is requested and no supplier is contacted.

Project sourcing — RFQ

Define species, system, production target and site conditions, size the requirement with the planning tools, and build one structured RFQ. Manufacturer research follows the requirement.

  • FishMatch helps prepare aquaculture RFQs and source relevant suppliers.
  • Supplier and manufacturer listings are provided for independent research, transparency and reference. Listing does not constitute certification, endorsement, qualification for a specific project or automatic introduction.
  • Buyer follow-up and supplier selection are handled by FishMatch.

There is no instant or automated supplier match. Manufacturer research happens after the project requirement is clear and is reviewed by the FishMatch team before any supplier is approached.

Manufacturers can register in the free directory and keep their company details up to date. Being listed is a research and visibility surface — it does not create an automatic connection to buyers, and it does not replace the human sourcing process.

Supplier and manufacturer listings are provided for research, transparency and discovery only. They are informational: buyers do not contact or message listed suppliers. Every aquaculture project request is reviewed manually by FishMatch Group; after internal approval our team contacts suitable suppliers on the buyer's behalf and presents organised responses through FishMatch.

Commercial project route

Is your project in Norway a fit?

FishMatch Group handles commercial B2B projects with a total budget of USD 250,000 or more — new farms, hatcheries, RAS, cages, processing or expansions. The buyer sends one brief; our team reviews and structures the RFQ, then approaches suitable suppliers on the buyer's behalf. Buyers are not put in direct contact with manufacturers at this stage. Smaller or idea-stage projects can start with the calculators below and send the RFQ once scope and budget are clearer.

Which inputs change the estimate and the RFQ?

Calculator results and supplier quotes both depend on: species and life stage, production target (tonnes per year or PL per cycle), water source and quality (temperature, salinity, flow), system design (pond, cage, RAS, hatchery, processing), site and access, energy supply and price, permits, and timeline.

Calculator figures are planning estimates based on stated assumptions — not engineering designs or supplier quotes. Growth, survival and output depend on project-specific biology and operating conditions and are never guaranteed. Formulas, assumptions and sources: calculator methodology.

2. Equipment & project sourcing

Send a structured RFQ. A person checks scope and budget before any supplier is approached.

Start the project RFQ

3. Financing (separate)

Financing is a separate track. FishMatch Group does not lend or guarantee financing.

Aquaculture financing

More on Norway

Each page answers a different stage of the same project — market, suppliers, feasibility and equipment.

Before you request quotes

Equipment scope

What equipment does a commercial aquaculture project actually need?

A grow-out project typically needs holding infrastructure (tanks, ponds or cages), water movement (pumps, piping, valves), aeration or oxygenation, water treatment appropriate to the system, feeding equipment, grading and handling gear, monitoring and alarms, and backup power. RAS adds mechanical filtration, biofiltration, degassing, disinfection and tighter process control. Hatchery and processing scopes are specified separately.

Which equipment should be specified before requesting quotes?

Specify the items whose sizing changes everything downstream: design biomass and stocking density, water exchange or recirculation rate, oxygen demand at peak temperature, and installed pumping head. With those four fixed, suppliers can quote aeration, filtration, pumps and power on the same basis. FishMatch calculators produce these figures and attach them to the RFQ.

Can equipment be sourced in stages?

Yes, and phased procurement is common. The usual sequence is water supply and holding infrastructure, then aeration and treatment, then automation and monitoring, then processing and cold chain. Staging works when interfaces and capacity headroom are defined at the start; otherwise later phases force replacement rather than addition.

Supplier selection criteria

How should a buyer compare aquaculture suppliers?

Compare on evidence, not on presentation: delivered projects at a similar scale and climate, engineering support during design, lead time commitments, spare-part and service availability in your region, certification and testing documentation, payment and warranty terms, and willingness to quote against your specification rather than substituting a catalogue package.

What are the warning signs in a supplier quotation?

Treat these as review triggers: no itemised scope, guaranteed biological or financial performance, no named delivery terms or lead time, no spare-parts or service statement, unclear responsibility for installation and commissioning, and equipment sizing that does not reference your water temperature, oxygen demand or biomass targets.

How does FishMatch handle supplier selection?

FishMatch is an independent sourcing service, not a manufacturer or reseller. The buyer submits one structured project request; our team reviews it first and only then contacts suitable suppliers on the buyer's behalf, presenting their responses through FishMatch in a comparable format. Buyers do not contact suppliers directly and nothing is sent automatically. The final choice stays with the buyer.