Commercial Shrimp Feed Plant — Example Project, Investment Range & Equipment Plan
A worked example of an extruded / pelleted vannamei shrimp feed mill sized at 5–30 t/hour (≈ 30,000–200,000 t/year). Use the indicative CAPEX bands, equipment categories, risk register and RFQ path as a planning starting point — then adapt the design to your target species, feed types (starter, nursery, grower, broodstock) and regional raw-material availability.
Project assumptions
Score your project in 60 seconds
Set your current status on seven factors. We calculate a 0–100 readiness score, flag gaps EPCs and lenders will raise, and pre-fill an RFQ your concierge can act on immediately.
Planning — foundational work still open, but structured RFQs feasible
- Energy plan: Grid connection secured
- CAPEX clarity: USD 2M–10M — mid commercial
- Sign a site option or lease for at least 20 years
- Commission water lab tests (salinity, TAN, iron, TDS) and file abstraction permit
- Engage local permitting consultant and file EIA scoping
- Secure at least one signed LOI from a processor or importer
Indicative execution readiness. Not a credit decision or engineering warranty.
System stack
Intake, cleaning & storage
- • Truck / rail / ship intake with sampling and moisture check
- • Magnets, drum sieves and destoners upstream of storage
- • Silo farm for major raw materials (20–40 silos, 100–500 t each)
- • Bagged / big-bag store with dosing station for minors and premixes
Dosing, grinding & mixing
- • Automated multi-scale dosing tied to formulation software
- • Pre-grinder (hammer mill) + fine grinder (ultra-fine ≤ 250 µm for shrimp)
- • Double-shaft paddle mixer with liquid addition (oils, molasses, phospholipids)
- • Post-mix sifter and buffer bin ahead of conditioning
Extrusion & pelleting
- • Twin-screw extruder (preferred for shrimp) with steam conditioner and DDC
- • Die-plate configuration for micro (0.8–1.5 mm) and standard (2.0–2.8 mm)
- • Optional pellet mill line (large-die grower) with steam conditioner
- • Crumbler and screens for starter / nursery size classes
Drying, cooling & coating
- • Belt or fluidised-bed dryer with heat recovery
- • Counter-flow cooler to ≤ ambient + 5 °C
- • Vacuum coater (batch) for high-fat / squid-oil / astaxanthin loads
- • Post-coating cooler and buffer bin ahead of packing
Packing & finished goods
- • Bagging lines: 25 kg valve bags, 500 kg / 1000 kg big-bags
- • Metal detection, check-weighing and inkjet lot / date coding
- • Palletiser + stretch-wrapper; optional silo truck loadout for bulk
- • Finished-goods warehouse with FIFO racking and traceability tags
Quality control & laboratory
- • NIR analysers on intake for protein, fat, moisture, fibre, ash
- • Wet lab: proximate, amino acids, mycotoxins, salmonella, PAP
- • Water stability, sinking rate and durability (PDI) testing per batch
- • Retention sample program per batch tied to lot code and BL
Formulation & compliance
- • Least-cost formulation software (Format, Adifo, Brill or equivalent) with live raw-material prices
- • Species-, stage- and market-specific nutrient constraints
- • GMP+ / FAMI-QS / FEMAS documentation and internal audit program
- • Optional ASC-Feed / MarinTrust chain-of-custody for sustainable claims
Utilities & energy
- • Installed electrical load 1.5–6 MW depending on capacity
- • Steam boiler (LPG / natural gas / biomass) 3–15 t/h
- • Compressed air, cooling water and dust-extraction / bag-filter network
- • Solar-hybrid option for daytime auxiliary loads and warehousing
Automation & controls
- • Plant-wide PLC + SCADA covering intake, dosing, extrusion, coating, packing
- • MES / ERP integration for batch, lot and traceability records
- • Energy sub-metering (kWh/tonne) per section and per product family
- • OEE dashboards: uptime, yield, giveaway, rework and micro-stops
Model this project on the page
Adjust the inputs to match your site and load profile. Outputs update live and can be sent as a pre-filled, confidential RFQ to project-matched suppliers.
Operating Cost (OPEX) Calculator
OPEX drives profitability more than CAPEX for most farms. This tool sums the major operating costs — feed, electricity, labor, fingerlings, water and maintenance — and expresses the total as $/month and $/kg produced.
Estimates Only: This calculator is provided for general informational purposes only. Results are approximate and may contain errors, omissions, or outdated information. They do not constitute legal, financial, engineering, tax, technical, or professional advice. Users are solely responsible for independently verifying all calculations, specifications, prices, regulations, and requirements with qualified professionals before making any decisions. By using this calculator, you acknowledge that the website owners, operators, and affiliates accept no responsibility or liability for any loss, damage, or decisions resulting from its use.
Commercial Aquaculture CAPEX Estimator
Rapid CAPEX for a commercial fish farm, shrimp farm, RAS plant or sea-cage project. Sizes total investment from target production, applies system-specific CAPEX/kg benchmarks, then breaks it into the six lines every bank wants: land & civil, process equipment, engineering & permitting, working capital, contingency and financing costs.
Drives base CAPEX per tonne of annual capacity.
Feed + energy + labor + overhead per kg.
Estimates Only: This calculator is provided for general informational purposes only. Results are approximate and may contain errors, omissions, or outdated information. They do not constitute legal, financial, engineering, tax, technical, or professional advice. Users are solely responsible for independently verifying all calculations, specifications, prices, regulations, and requirements with qualified professionals before making any decisions. By using this calculator, you acknowledge that the website owners, operators, and affiliates accept no responsibility or liability for any loss, damage, or decisions resulting from its use.
Aquaculture Financing & Loan Amortization Calculator
Lender-side view of a commercial aquaculture loan: monthly and annual debt service, total interest paid, interest-during-construction (IDC) and the resulting DSCR at your projected EBITDA. Use before approaching a bank, EXIM agency or aquaculture-specialist fund.
Interest-only period during construction and biomass ramp.
Estimates Only: This calculator is provided for general informational purposes only. Results are approximate and may contain errors, omissions, or outdated information. They do not constitute legal, financial, engineering, tax, technical, or professional advice. Users are solely responsible for independently verifying all calculations, specifications, prices, regulations, and requirements with qualified professionals before making any decisions. By using this calculator, you acknowledge that the website owners, operators, and affiliates accept no responsibility or liability for any loss, damage, or decisions resulting from its use.
Project ROI Calculator
Bank-ready snapshot: payback years, annual ROI% and simple 5-year return. Pair with the RAS / project cost calculator for CAPEX.
Estimates Only: This calculator is provided for general informational purposes only. Results are approximate and may contain errors, omissions, or outdated information. They do not constitute legal, financial, engineering, tax, technical, or professional advice. Users are solely responsible for independently verifying all calculations, specifications, prices, regulations, and requirements with qualified professionals before making any decisions. By using this calculator, you acknowledge that the website owners, operators, and affiliates accept no responsibility or liability for any loss, damage, or decisions resulting from its use.
Project stages
- 1. Market & product strategyTarget species, farm mix, feed portfolio, price positioning, expected offtake. 4–8 weeks.
- 2. Feasibility & conceptCapacity plan, extruder sizing, silo count, utilities, class-3 budget. 8–12 weeks.
- 3. Permits & site preparationEIA, air/dust permits, water abstraction, discharge, GMP+ readiness plan. 3–9 months.
- 4. RFQ & supplier selectionNeutral RFQ for extrusion, coating, silos, packing, controls, buildings and lab. 10–14 weeks.
- 5. Construction & installationCivil, silo farm, extrusion tower, coating, packing, warehouse. 12–18 months.
- 6. Commissioning & qualificationExtruder trials, first commercial batches, water-stability validation, farm trials. 3–6 months.
- 7. Steady-state productionRamp to nameplate over 6–12 months while formulation, yield and OEE stabilise.
Main CAPEX drivers
Indicative share of total installed cost. Actual split varies by region, redundancy, automation and civil scope.
| Extrusion & pelleting lines | 18–24% |
| Silo farm, intake & storage | 14–20% |
| Drying, cooling & vacuum coating | 10–14% |
| Buildings, civil works & warehousing | 12–18% |
| Grinding, mixing & dosing | 6–10% |
| Packing, palletising & loadout | 5–8% |
| Utilities (boiler, air, electrical) | 8–12% |
| Automation, PLC / SCADA & MES | 5–8% |
| Engineering, permits & project management | 5–8% |
| Contingency (recommended) | 10–15% |
Bankability questions
- Is farm-side demand secured through captive farms, offtake contracts or a defined regional shortage?
- Are raw-material sources (fishmeal, SPC, oils, vitamins) diversified across suppliers and geographies?
- Is the plant designed for shrimp-specific requirements (ultra-fine grinding, twin-screw extrusion, vacuum coating, water stability > 2 h)?
- Is the feed portfolio (starter → grower → broodstock) defined with target CP, digestibility and stability specs?
- Is GMP+ / FAMI-QS / FEMAS certification part of the launch plan, with an internal QA lead identified?
- Is CAPEX supported by class-3 estimates from at least two independent aquafeed OEMs or EPC providers?
- Is OPEX modelled at pessimistic, base and optimistic raw-material, FX and energy scenarios?
- Is working-capital financing sized for 60–120 days raw-material inventory + finished-goods buffer?
- Is a trials / adoption plan agreed with target farms before commissioning?
- Are biosecurity, mycotoxin and residue risks addressed by intake QC, storage design and formulation limits?
Key project risks
- Fishmeal / SPC / oil price shocks compress margins if not passed through in feed price fast enough.
- Poor water stability or digestibility causes farmer rejection and long win-back cycles.
- Mycotoxin contamination on cereal ingredients triggers batch recalls and reformulation.
- Extruder downtime idles the whole plant — redundancy, spares and training are critical.
- FX volatility on imported raw materials (often USD-denominated) hits local-currency P&L.
- Loss of GMP+ / FAMI-QS certification or a residue finding blocks premium buyers and export sales.
- Local demand shift (disease outbreak on farms, price crash) can cut orders 20–40% for months.
Common questions
Get the bankability brief — Shrimp Feed Plant Example Project
6-page investor-grade brief: CAPEX bands, OPEX assumptions, revenue model, sensitivity, risk register and a country permit map — tailored to this archetype. Free, sent to your inbox and printable to PDF.
Turn this Shrimp Feed Plant Example Project archetype into a real RFQ
FishMatch Group prepares a neutral, confidential brief based on the assumptions, system stack and cost drivers on this page — then matches you with 1–3 project-matched international suppliers or EPC partners. Supplier identities stay private until you approve them. Buyers never pay.
Answer a short guided form — species, capacity, site, timeline, budget range. Takes ~3 minutes. Fully confidential.
Our team screens project-matched providers globally and prepares a comparable, budget-grade RFQ package for each.