Normalising the offers
Every proposal is mapped back onto the RFQ lot structure. Anything missing is either requested or priced as an adder, so the comparison reflects the same delivered scope in every column.
- ·Scope alignment against each lot and interface point
- ·Currency, incoterms, packing and inland transport put on the same basis
- ·Installation, supervision, commissioning days and training compared explicitly
- ·Spares, consumables and warranty duration valued, not ignored
- ·Energy and consumable duty checked against the sizing basis
- ·Lead time and payment milestones set side by side
Technical deviations matter more than price
A supplier who quotes a smaller biofilter is not cheaper — they are quoting a different farm. Deviations are listed one by one and the buyer decides which are acceptable, rather than discovering them during commissioning.
How the introduction actually happens
FishMatch is not an automatic marketplace. There is no button that releases your details to a network. Introductions are made by a person, to the specific suppliers you want to speak with, after the review — and contracting is directly between you and the supplier.
Where financing fits
For suitable projects, independent financing partners can be introduced. They assess the project on their own terms. FishMatch does not lend, approve credit, set rates or give financial advice.
How to compare shrimp and fish farm equipment quotes line by line
Two quotes for the same farm routinely differ by forty percent, and the lower one is rarely cheaper. The difference lives in exclusions: one aeration quote includes mounting, cabling and commissioning, the other is ex-works hardware. One drum filter price includes the control panel and bypass, the other lists them as options on page nine. Comparing totals before normalising scope is how buyers end up paying more for the 'cheaper' offer.
The working method is a normalisation sheet. Rebuild every offer onto your RFQ lot structure, one line per item. Mark every missing item and price it as an adder from the other offers or from budget rates. Convert to one currency and one delivery term. What remains is the real ranking — and it is common for the middle-priced headline to become the best-value offer once commissioning, spares and warranty are counted. For shrimp equipment specifically, pay attention to what happens after the sale: paddlewheel gearbox spares, liner warranty terms and local service cover decide operating cost long after the purchase price is forgotten.
- ·Normalise scope before comparing any totals
- ·Price every gap as an adder — an incomplete offer is not a cheap offer
- ·Weight warranty, spares and service cover, not just day-one price
Reading shrimp farm equipment quotes: what to check first
Shrimp farm equipment quotes cluster around a handful of lots — aeration, pumping, liners, feeders, water quality monitoring and harvest handling — and each has a familiar trap. Aeration is quoted as paddlewheel units rather than as installed kW per hectare at your target biomass, so two offers can look identical and deliver different oxygen. Pumps are quoted at a duty point nobody checked against the real static head. Liners are quoted by thickness without UV grade or welding scope. Feeders are quoted without control, mounting or spares.
Compare them by duty and delivered scope, not by unit count: installed aeration kW per hectare, pumped exchange in percent of pond volume per day, liner grade with installation and welding included, feeder throughput with control and mounting. Then ask each supplier the same three post-sale questions — spares lead time, service coverage in your country, and warranty start date — because on shrimp projects those decide the operating cost far more than the purchase price does. The same discipline applies when comparing fish farm equipment suppliers for RAS and cage projects: drum filters by screen area and backwash volume, biofilters by media volume at your TAN load, oxygen systems by transfer efficiency at your flow — never by headline package price.
- ·Aeration: compare installed kW per hectare at peak biomass, not unit count
- ·Pumps: confirm the duty point against real static head and pipe losses
- ·Liners: grade, UV rating, welding and installation must be in or out explicitly
- ·Post-sale: spares lead time, in-country service and warranty start date