RAS Planning: From Production Target to Bankable RFQ
RAS planning is a sequence, and the order matters: target, site, sizing, cost, feasibility, RFQ. Skip a step and you buy it back later — at redesign prices. This is the six-step path, with a tool at each one.
Supplier and manufacturer listings are provided for research, transparency and discovery only. FishMatch Group does not provide automatic buyer-supplier introductions. Every aquaculture project request is reviewed manually by David / FishMatch Group, and supplier introductions are made only after internal approval.
The six-step RAS planning sequence
- 1
Define the production target and market
Tonnes per year, species, harvest size and the price your market actually pays. Every downstream number — tank volume, flow, CAPEX, OPEX — derives from this, so a vague target guarantees a vague budget.
- 2
Qualify the site and water source
Water chemistry, temperature profile, discharge limits, grid capacity and tariff. Climate and water source move RAS cost more than any equipment brand; a brackish well or waste-heat source can change feasibility outright.
- 3
Size from feed load, not tank volume
Biofilter capacity, oxygen duty and pump flow are set by kilograms of feed per day. Sizing from nameplate tank volume is the single most common cause of underperforming RAS — and of quotes that can't be compared.
RAS sizing calculator - 4
Build the cost model before any quote
Model CAPEX per tonne and OPEX per kilogram with your own tariff and feed price. Feed and energy are 55–70% of OPEX; if the model only works at optimistic prices, the project doesn't work.
RAS cost calculator - 5
Stress-test feasibility and contingency
Carry 10–15% contingency, model a survival or price downside, and check the plan against the 10 planning mistakes. Lenders will do this for you — better to find the gaps first.
Run the planning check - 6
Issue a comparable, human-reviewed RFQ
A scoped RFQ with identical line items is the only way quotes become comparable. FishMatch reviews every brief, then runs confidential outreach to project-matched suppliers — never an automatic marketplace.
Request a human-reviewed quote
Check the plan against the 10 mistakes
Before any RFQ goes out, walk the plan through the 10 aquaculture, RAS and shrimp farm planning mistakes guide — sizing basis, water qualification, redundancy, contingency and scope comparability. Or let the planning check tool score your project against the same checklist and prefill an RFQ with the gaps flagged.
Planning resources
RAS planning FAQ
Ready to move from plan to quotes?
Submit your project brief. A person reviews every RFQ before any supplier is contacted, and sourcing starts only after that review — suppliers never see you, and you never see them, until the match is right.