RAS design

RAS system design: the scope every quote must cover

A recirculating aquaculture system is a chain of linked packages — filtration, biofiltration, CO₂ removal, oxygen, disinfection, pumping, controls, backup power and effluent — all sized from one design basis: species, biomass and peak feed load. Fix that basis and the scope of each package before asking suppliers to quote, so you compare like with like.

Planning guidance only. Final sizing must be done and signed off by a qualified RAS engineer.

What data makes a RAS design responsibly quotable?

Provide species and life stage, production schedule, peak biomass and feed, seasonal water analysis, site conditions and utility availability. Then define every package’s flow, load, operating conditions, interfaces and acceptance tests. A tank-volume-only proposal cannot establish treatment capacity; indoor, pond and sea-cage designs are not interchangeable.

Inputs and preliminary calculations
The RAS flow and oxygen estimator uses your peak feed, protein fraction, turnover and water volume. Its editable 0.25 kg O₂/kg feed and 0.092 TAN factor are attributed to Timmons & Ebeling (2010), not whole-farm performance guarantees. Document microbial loads and transfer losses separately without double counting.
What buyers compare
Treatment capacity at stated temperature and salinity; useful oxygen transfer; pump duty and head; independent backup; civil and installation exclusions; commissioning tests, training, warranty and spares. Use the same design basis for every response.

Can a preliminary design predict farm yield?

No. Growth, survival, FCR and annual output must be supported by your production plan and relevant evidence. Test your own energy, selling-price and ramp-up assumptions in the CAPEX/OPEX/payback scenario; obtain engineering review before purchasing or financing.

Process reference: FAO/Eurofish, A Guide to Recirculation Aquaculture (2015). Source checked 13 October 2026. This checklist is FishMatch’s procurement synthesis, not design certification. Project scoping guide · For solution providers.

1. Design basis: species, biomass and feed load

Every package below is sized from the same basis: species, annual output, harvest weight, maximum standing biomass and peak daily feed. Agree it in writing before any supplier sizes equipment, or quotes cannot be compared.

Ask every supplier to state

  • Peak feed per day (kg) and feed protein %
  • Maximum stocking density per tank group
  • Water temperature and salinity range
RAS sizing calculator

2. Water source, intake and make-up water

Source type (well, municipal, surface, sea), chemistry, temperature and daily make-up volume. Pre-treatment needs depend on the source analysis, not on the supplier's standard design.

Ask every supplier to state

  • Lab water analysis attached
  • Make-up water % of system volume per day
  • Pre-treatment included or excluded

3. Mechanical filtration and solids removal

Drum or disc filters, screen mesh size, backwash water use and fine-solids handling. Solids load follows feed load.

Ask every supplier to state

  • Screen micron size
  • Backwash water and power use
  • Sludge flow to effluent treatment

4. Biofiltration (nitrification)

Media type (MBBR, fixed bed, trickling), media volume and specific surface area, sized from the daily ammonia load produced by feed.

Ask every supplier to state

  • Design ammonia load (g TAN/day) and how it was derived
  • Media volume and specific surface area
  • Assumed nitrification rate at design temperature
Biofilter sizing calculator

5. Degassing and CO₂ stripping

CO₂ builds up with feed and oxygen use. Strippers, aeration columns and air-to-water ratios must be stated with the target CO₂ level.

Ask every supplier to state

  • Target dissolved CO₂ (mg/L)
  • Stripper type and air-to-water ratio
  • Fan power

6. Oxygenation

Oxygen demand from biomass and feed, supply method (LOX, on-site generator, cones, low-head oxygenators) and the backup oxygen source.

Ask every supplier to state

  • Design oxygen demand (kg O₂/day)
  • Primary and emergency oxygen supply
  • Dissolved-oxygen setpoint per tank
Oxygen requirement calculator

7. Disinfection: UV and/or ozone

UV dose and the flow it treats, ozone dosing and residual control. State whether intake water, recirculating water or both are treated.

Ask every supplier to state

  • UV dose at end of lamp life
  • Treated flow (side-stream or full flow)
  • Ozone residual monitoring

8. Pumping and hydraulics

Recirculation flow, tank exchange rate, total head and pump efficiency drive the largest continuous power use in most RAS.

Ask every supplier to state

  • Design flow and total dynamic head
  • Pump efficiency and installed kW
  • Duty/standby pump arrangement
Energy cost calculator

9. Tanks and production layout

Tank volume, number, material and grouping into independent loops for biosecurity and staged production.

Ask every supplier to state

  • Tank count, volume and material
  • Number of independent loops
  • Purge/depuration tanks included?

10. Monitoring, controls and alarms

Sensors (O₂, temperature, pH, CO₂, flow, level), PLC/SCADA scope and remote alarms. Specify what is monitored per tank versus per loop.

Ask every supplier to state

  • Sensor list per tank and per loop
  • Alarm escalation and remote access
  • Software licences and support term

11. Backup power and redundancy

Generator capacity, automatic transfer time and which loads it carries. Single points of failure (one blower, one oxygen line) should be named and priced out.

Ask every supplier to state

  • Generator kVA and transfer time
  • Loads carried in a power failure
  • List of single points of failure

12. Effluent, sludge and discharge permit

Sludge thickening, treatment and disposal route, matched to the local discharge permit. Often excluded from equipment quotes and added later.

Ask every supplier to state

  • Effluent treatment scope included or excluded
  • Sludge volume and disposal route
  • Permit limits the design meets

13. Building, civil works and installation

Building, floor loading, insulation, HVAC, civil works, installation, commissioning and training — the lines most often left out of an equipment-only price.

Ask every supplier to state

  • Which of these are in scope (FAT/SAT, installation, commissioning)
  • Performance guarantees and their test conditions
  • Warranty and spare parts

From design scope to comparable quotes

Estimate the budget with the RAS cost calculator, then use the FishMatch procurement platform to send one scope to several suppliers. Every request is reviewed by a person; FishMatch is supplier-neutral and handles projects from USD 250,000.

Compare equipment on one project basis

RAS packages: interfaces, operating cost and acceptance

  • State species and life stage, peak feed in kg/day, biomass in kg, water flow in m³/h, temperature and salinity; annual tonnes alone cannot size treatment.
  • Compare mechanical capture, TAN conversion, CO₂ removal and useful oxygen transfer as separate duties; document losses and avoid counting demand twice.
  • Price pumps at total dynamic head, oxygen supply, heating/cooling, backwash, sludge, sensor calibration, UV consumables and operator cover; declare tariff and hours.
  • Request a responsibility matrix for tanks, treatment, civil works, power, controls, installation and commissioning. Name single points of failure and tested standby arrangements.
  • Acceptance tests must name water conditions, measured loads, instruments, test duration, remedies and handover evidence. A capacity claim or manufacturer reference is not a farm-output guarantee.

Buyers pay no fee. Managed equipment projects start at USD 250,000. Supplier identities remain private; human review precedes outreach. No stock, price, performance or financing is guaranteed.

Prepare an equipment RFQ

Sources: RAS design coefficients (Timmons & Ebeling)

The water-treatment figures used in our RAS and farm-cost tools come from these published references. They are design starting points — your system engineer and equipment suppliers confirm final values.

What it measuresCoefficientSourceOriginal wording (source)
Ammonia (TAN) producedTAN (kg/day) = feed (kg/day) × protein fraction × 0.092Timmons & Ebeling et al., NRAC Publication 01-002 (2002)“PTAN = F * PC * 0.092 … The constant in the ammonia generation equation assumes that protein is 16% nitrogen, 80% nitrogen is assimilated by the organism, 80% assimilated nitrogen is excreted, and 90% of nitrogen excreted as TAN + 10% as urea.” — Ebeling, Timmons & Bisogni, citing Timmons et al. (2002)
Oxygen used by the fishAbout 0.25 kg O₂ per kg feed (design value; adjust by species and temperature)Timmons & Ebeling et al., NRAC Publication 01-002 (2002)“POxygen = − 0.25 kg per kg feed consumed by fish (a negative production term) − 0.12 kg per kg feed consumed by nitrifying bacteria − 0.13 heterotrophic bacteria (estimate, can be as high as 0.5) = − 0.50 kg … per kg feed for system.” — Timmons, Mass Balances, Loading Rates and Fish Growth (Cornell / ISTA 7 RAS workshop, 2006)
Carbon dioxide producedAbout 1.375 kg CO₂ per kg O₂ consumed (44 ÷ 32 molar ratio)Timmons & Ebeling et al., NRAC Publication 01-002 (2002)“PCO2 = 1.375 grams produced for each gram O2 consumed (both fish and bacteria).” — Timmons, Mass Balances, Loading Rates and Fish Growth (Cornell / ISTA 7 RAS workshop, 2006)
Nitrification: oxygen useAbout 4.18 g O₂ per g ammonia-nitrogen convertedEbeling, Timmons & Bisogni, Aquaculture 257 (2006) 346–358“For every g of ammonia-nitrogen converted to nitrate-nitrogen, 4.18 g of dissolved oxygen, and 7.05 g of alkalinity (1.69 g inorganic carbon) is consumed and 0.20 g of microbial biomass (0.105 g organic carbon) and 5.85 gm of CO2 … is produced.” — Ebeling, Timmons & Bisogni (2006)
Nitrification: alkalinity useAbout 7.05 g alkalinity (as CaCO₃) per g ammonia-nitrogen convertedEbeling, Timmons & Bisogni, Aquaculture 257 (2006) 346–358“It should be noted that both the consumption of oxygen and alkalinity is less than that which normally reported, 4.57 g of O2 and 7.14 g of alkalinity for every g of ammonia-nitrogen converted (Timmons et al., 2002), because in this equation some of the ammonia-nitrogen is converted to biomass.” — Ebeling, Timmons & Bisogni (2006)
  1. Timmons, M.B., Ebeling, J.M., Wheaton, F.W., Summerfelt, S.T. & Vinci, B.J. (2002). Recirculating Aquaculture Systems, 2nd ed. NRAC Publication No. 01-002. Cayuga Aqua Ventures, Ithaca, NY.
  2. Ebeling, J.M., Timmons, M.B. & Bisogni, J.J. (2006). Engineering analysis of the stoichiometry of photoautotrophic, autotrophic, and heterotrophic removal of ammonia–nitrogen in aquaculture systems. Aquaculture 257, 346–358. doi:10.1016/j.aquaculture.2006.03.019 · Author paper text: Aquacultural Engineering Society (PDF)
  3. Timmons, M.B. (2006). Mass Balances, Loading Rates, and Fish Growth — course notes, RAS short course, Cornell University / 7th International Symposium on Tilapia in Aquaculture. University of Arizona (PDF)

RAS layout choices compared

Layout decides how far a disease or equipment failure can spread and how much you can expand later. Ask designers to explain why they chose a layout for your species and output.

LayoutTypical fitAsk the designer to stateWatch-outs
Single shared loopSmall farms and pilot systemsTreatment capacity per tank and isolation valvesOne problem reaches every tank
Several independent loopsCommercial grow-out and staged productionNumber of loops, what is shared (oxygen, power, controls)More equipment to buy and maintain
Partial reuse (PRAS)Sites with good water and lower budgetsDaily water exchange, intake treatment and discharge permitDepends on water availability and discharge rules
Separate hatchery / nursery loopFarms producing their own juvenilesBiosecurity barrier between life stagesShared staff or equipment can break the barrier

General buyer guidance, not a recommendation of any supplier. FishMatch Group is a buyer-side sourcing service, not a manufacturer.

Get comparable quotes in 3 steps

  1. 1

    Describe your project

    Species, target output, site and budget range. Rough numbers are fine.

  2. 2

    We review and structure it

    A person checks your request and turns it into a comparable RFQ. Procurement help is for projects of USD 250,000 and above.

  3. 3

    Compare proposals

    You receive proposals on the same basis. Supplier identities stay private until you choose to proceed.

Send a RAS request

Short answer

How do you prepare a reviewed RFQ for RAS System Design?

Submit a private request for RAS System Design with the country, scope, capacity or volume and timing. FishMatch Group is a human-reviewed sourcing and RFQ platform within Global B2B Group: its team clarifies the requirement, researches independent providers and helps compare any replies. It is not the producer, supplier, contractor or operator. No quotation, availability or outcome is guaranteed; the buyer decides whether to proceed.

How it works:
One structured request, human-reviewed before any supplier outreach
Typical turnaround:
Depends on scope and site data; no turnaround is guaranteed
Confidentiality:
Supplier names are never exposed during evaluation
Cost to buyers:
No fee charged to the buyer
How do you prepare a reviewed RFQ for RAS System Design?

Submit a private request for RAS System Design with the country, scope, capacity or volume and timing. FishMatch Group is a human-reviewed sourcing and RFQ platform within Global B2B Group: its team clarifies the requirement, researches independent providers and helps compare any replies. It is not the producer, supplier, contractor or operator. No quotation, availability or outcome is guaranteed; the buyer decides whether to proceed.

How does FishMatch Group source suppliers for this requirement?

Submit a private RFQ with the country, product or project scope, capacity or volume and timing. The FishMatch team reviews it, clarifies missing details and researches independent providers before approved outreach. Any received proposals are compared on the same scope; FishMatch is not the supplier, manufacturer, contractor or operator, and does not guarantee a response or outcome.

Do buyers see supplier names during the sourcing process?

No. Supplier identities stay confidential during discovery and evaluation. You receive anonymised, comparable technical and commercial packages, and introductions happen only after both sides are qualified and agree to proceed.

Before you request quotes

Equipment scope

What equipment does a commercial aquaculture project actually need?

A grow-out project typically needs holding infrastructure (tanks, ponds or cages), water movement (pumps, piping, valves), aeration or oxygenation, water treatment appropriate to the system, feeding equipment, grading and handling gear, monitoring and alarms, and backup power. RAS adds mechanical filtration, biofiltration, degassing, disinfection and tighter process control. Hatchery and processing scopes are specified separately.

Which equipment should be specified before requesting quotes?

Specify the items whose sizing changes everything downstream: design biomass and stocking density, water exchange or recirculation rate, oxygen demand at peak temperature, and installed pumping head. With those four fixed, suppliers can quote aeration, filtration, pumps and power on the same basis. FishMatch calculators produce these figures and attach them to the RFQ.

Can equipment be sourced in stages?

Yes, and phased procurement is common. The usual sequence is water supply and holding infrastructure, then aeration and treatment, then automation and monitoring, then processing and cold chain. Staging works when interfaces and capacity headroom are defined at the start; otherwise later phases force replacement rather than addition.