FAT vs SAT Decision Guide for Aquaculture Equipment Procurement
Factory Acceptance Tests (FAT) and Site Acceptance Tests (SAT) are the two most powerful — and most misunderstood — levers in aquaculture equipment procurement. Use the wrong one, or skip one, and a $2M process skid becomes a site delay and a warranty dispute. This decision guide explains when each applies and exactly what to ask suppliers before you sign.
1. What FAT and SAT actually mean
FAT is a structured test at the supplier's factory before shipment. It proves that the equipment meets the contractual specification, runs through its design operating envelope, and produces the promised outputs. SAT is a structured test at your site after installation and commissioning. It proves that the same equipment works in your building, with your utilities, your water, your staff and your product.
- FAT = 'Did the supplier build what we ordered?'
- SAT = 'Does it work in our real-world conditions?'
- Both are contract gates, not friendly demonstrations
- Both need signed protocols, witnessed tests and non-conformance procedures
2. When to require FAT
Require FAT whenever finding a defect after shipment is expensive, slow or technically risky. For aquaculture projects, that almost always means custom-fabricated skids, overseas suppliers, long-lead mechanical packages and anything with a control system that must be proven before it leaves the factory.
- Custom RAS process skids (biofilters, drum filters, oxygen cones, UV/ozone units)
- Equipment over ~USD 100K where sea freight and customs add weeks to any rework
- Control panels, PLCs and SCADA systems that need IO checks before site power-up
- Processing lines where changeover, yield and throughput must be demonstrated
- Any item where the supplier's reference plant is not identical to your scope
3. When to require SAT
SAT is mandatory for any equipment whose performance depends on site conditions the supplier cannot replicate in its factory. Even a perfect FAT does not guarantee the same machine will hit specification once it is bolted to your floor and connected to your water and power.
- Equipment tied to civil works, foundations and utility interfaces
- Systems using site water chemistry, salinity, temperature or pressure
- Installations where local voltage, frequency or ambient conditions differ from the factory test bed
- Any scope with biological ramp-up (biofilters, RAS loops, nursery systems)
- Integrated lines where multiple vendor packages must operate together
4. The decision matrix
Most major aquaculture packages need both. The question is what percentage of the acceptance risk sits in the factory versus on site. Use this matrix to set the right weight in the contract.
- Overseas custom skid with complex controls → FAT heavy + SAT light
- Locally built tank or pipe rack with simple duty → SAT only
- Processing line with imported machines + local civil → FAT on machines, SAT on full line
- RAS biofilter with site-specific water → FAT for mechanical integrity, SAT for biological performance
- Emergency spare pump from known brand → Receipt inspection only
5. What to ask suppliers about FAT
A weak FAT protocol is worse than no FAT because it creates a false sense of security. Ask these questions before the contract is signed, when the supplier still wants the deal.
- What is the exact test protocol and which acceptance criteria are pass/fail?
- Who pays for FAT — is it included in the contract price or a separate line?
- Can the Owner or Owner's Engineer witness the FAT without extra charge?
- What instrumentation will be used, and is it calibrated and traceable?
- What happens if a non-conformance is found — rework, replacement or credit?
- Which utilities, water and feed will the supplier use to simulate real duty?
- Will you receive a signed FAT report, video evidence and as-built test logs?
6. What to ask suppliers about SAT
SAT is where most warranty disputes begin. Make sure the contract defines the test conditions, the success criteria and the consequences of failure before the equipment leaves the factory.
- What is the SAT protocol, duration and operating envelope?
- Who provides water, power, staff, feed and biological material for the test?
- What are the guaranteed KPIs — throughput, energy, yield, availability, water quality?
- How many consecutive days of stable operation are required to pass?
- What is the punch-list process and how long does the supplier have to close items?
- Does SAT trigger the start of the warranty and performance-guarantee period?
- What documentation is delivered at SAT sign-off (O&M manuals, training records, spare-parts list)?
7. Structure payments around acceptance, not delivery
The strongest procurement lever is the payment schedule. Hold a meaningful retention until SAT is passed, not just until the truck arrives. A typical schedule for a major skid is 30% order, 30% readiness/FAT, 30% delivery/erection, 10% SAT. Never release the final tranche before documented acceptance.
8. Common mistakes
These errors recur on aquaculture projects of every size. Most are cheap to avoid at contract stage and expensive to fix on site.
- Accepting a 'visual inspection' instead of a witnessed FAT
- Skipping SAT because the equipment 'passed FAT'
- Not defining pass/fail criteria in writing
- Releasing final payment before SAT sign-off
- Letting the supplier write the protocol without Owner review
- Ignoring local utility conditions in the SAT envelope
Red flags to stop a tender
- Supplier refuses to allow Owner witness at FAT
- No written FAT or SAT protocol in the contract
- Payment terms release 100% before SAT
- Acceptance criteria are vague ('satisfactory performance')
- Supplier claims SAT is not needed because of FAT
- No spare-parts list or O&M manual tied to SAT sign-off
- Warranty starts on delivery instead of SAT/COD
Size it before you tender
FAQ
Supplier-neutral by design
FishMatch Group is not a reseller. We do not represent any single supplier. Every tender we support runs on a no-names basis until the Owner selects a shortlist.
Short answer
What do buyers need to know about Fat Vs Sat Aquaculture Equipment?
Fat Vs Sat Aquaculture Equipment affects both project cost and project risk, so it belongs in the specification stage rather than the purchasing stage. This page sets out what commercial buyers assess, what typically drives cost and lead time, and which questions to put to suppliers before signing. You can turn any of it into a confidential RFQ in a few minutes.
- Who it is for:
- Investors, operators and project developers specifying commercial systems
- Cost drivers:
- Capacity, water source, energy price, permitting and logistics
- Next step:
- Turn the requirement into a confidential RFQ
- Cost to buyers:
- No fee charged to the buyer
Before you request quotes
Equipment scope
What equipment does a commercial aquaculture project actually need?
A grow-out project typically needs holding infrastructure (tanks, ponds or cages), water movement (pumps, piping, valves), aeration or oxygenation, water treatment appropriate to the system, feeding equipment, grading and handling gear, monitoring and alarms, and backup power. RAS adds mechanical filtration, biofiltration, degassing, disinfection and tighter process control. Hatchery and processing scopes are specified separately.
Which equipment should be specified before requesting quotes?
Specify the items whose sizing changes everything downstream: design biomass and stocking density, water exchange or recirculation rate, oxygen demand at peak temperature, and installed pumping head. With those four fixed, suppliers can quote aeration, filtration, pumps and power on the same basis. FishMatch calculators produce these figures and attach them to the RFQ.
Can equipment be sourced in stages?
Yes, and phased procurement is common. The usual sequence is water supply and holding infrastructure, then aeration and treatment, then automation and monitoring, then processing and cold chain. Staging works when interfaces and capacity headroom are defined at the start; otherwise later phases force replacement rather than addition.
Supplier selection criteria
How should a buyer compare aquaculture suppliers?
Compare on evidence, not on presentation: delivered projects at a similar scale and climate, engineering support during design, lead time commitments, spare-part and service availability in your region, certification and testing documentation, payment and warranty terms, and willingness to quote against your specification rather than substituting a catalogue package.
What are the warning signs in a supplier quotation?
Treat these as review triggers: no itemised scope, guaranteed biological or financial performance, no named delivery terms or lead time, no spare-parts or service statement, unclear responsibility for installation and commissioning, and equipment sizing that does not reference your water temperature, oxygen demand or biomass targets.
How does FishMatch handle supplier selection?
FishMatch is an independent sourcing layer, not a manufacturer or reseller. Requirements are structured into a single technical RFQ and routed to relevant producers; buyers receive comparable offers without supplier identities being exposed before they choose to proceed. Selection stays with the buyer — FishMatch standardises the comparison basis.