Aquaculture project timelines: what to tell a client at concept stage
At concept stage, present a phase-based schedule with ranges rather than dates: design and feasibility, permitting, procurement and fabrication, construction and installation, commissioning, and biological ramp-up to steady state. Permitting and biological ramp-up are the phases most often compressed in client expectations and least controllable by suppliers.
- Show phases with ranges and named dependencies, never a single completion date at concept.
- Permitting duration is jurisdiction-specific — verify locally rather than assuming.
- Fabrication and shipping lead times vary by package; long-lead items should be identified early.
- Steady-state output arrives cycles after mechanical completion, not at handover.
Phases to present
- Concept and feasibility: design basis, site verification, budget bracketing.
- Permitting and land: environmental, water abstraction, discharge, construction.
- Procurement: specification, RFQ, evaluation, contract.
- Fabrication and shipping: long-lead items identified and ordered first.
- Construction and installation: civils, mechanical, electrical.
- Commissioning: water-on, functional testing, operator training.
- Biological ramp-up: first stocking through to design output.
Dependencies clients underestimate
- Water analysis results gating final treatment sizing.
- Grid connection approval gating commissioning.
- Seed availability windows gating first stocking.
- Operator recruitment and training gating stable performance.
How to phrase it
Use conditional language tied to decisions: 'procurement can start once the design basis is frozen; fabrication lead time then applies from contract signature'. This keeps the schedule honest and makes the client's own decisions visible as the critical path.