Planning · Timeline

Aquaculture procurement, phase by phase.

A realistic 12–18 month roadmap from feasibility to commissioning — with typical durations, deliverables per phase, and the bottlenecks that quietly extend most projects by 4–6 months.

  1. 1
    Month 1–2

    Feasibility & scoping

    Deliverables
    • Species and system selection (RAS, pond, cage, hybrid)
    • Site pre-screen: water source, energy, permitting risk
    • High-level CAPEX / OPEX band and IRR sensitivity
    • Off-take assumptions and market pricing
    Common bottlenecks
    • · Skipping water-quality and volume tests before locking a site
    • · Choosing a technology before defining the production target
    Start a project intake
  2. 2
    Month 2–4

    Concept design & basis of design

    Deliverables
    • Process flow diagram and mass balance
    • Hydraulic and oxygen budget
    • Preliminary layout, single-line electrical, HVAC concept
    • Bill of Quantities v0 across every major package
    Common bottlenecks
    • · Under-sized biofilter or oxygen system driving late redesigns
    • · No documented basis of design, forcing suppliers to guess
    Open the Planning Center
  3. 3
    Month 3–5

    Bankability & financing

    Deliverables
    • Full financial model with CAPEX phasing
    • Environmental permit strategy and biosecurity plan
    • Insurance strategy (asset + biological)
    • Bankable pack for lenders / grant agencies
    Common bottlenecks
    • · Model built on supplier list prices instead of quoted CAPEX
    • · Missing off-take LOIs and permit letters
    Download the bankability checklist
  4. 4
    Month 4–6

    RFQ preparation

    Deliverables
    • Package split (civil, water treatment, oxygen, feed, automation)
    • Technical spec + BOQ per package
    • Commercial terms: warranty, spares, training, performance guarantees
    • Short-list of project-matched suppliers per package
    Common bottlenecks
    • · Sending a single mega-RFQ instead of packaging by discipline
    • · Skipping performance guarantee wording, forcing renegotiation later
    Build the RFQ package
  5. 5
    Month 6–8

    Supplier evaluation & contracting

    Deliverables
    • Technical clarification rounds and normalised bid comparison
    • Reference visits or video walk-throughs
    • Contract negotiation: milestones, LDs, IP, spares, training
    • Signed contracts and down-payments
    Common bottlenecks
    • · Comparing bids on headline price instead of TCO
    • · No independent technical review before signing
    Compare on a TCO basis
  6. 6
    Month 8–14

    Manufacturing, delivery & installation

    Deliverables
    • Factory acceptance tests (FAT) for critical skids
    • Sea and inland freight planning, incoterms
    • Site acceptance tests (SAT) and mechanical completion
    • As-built drawings and O&M manuals
    Common bottlenecks
    • · Uncoordinated freight causing storage and demurrage costs
    • · Late civil handover blocking equipment installation
    Documentation center
  7. 7
    Month 14–18

    Commissioning & ramp-up

    Deliverables
    • Wet commissioning, biofilter maturation
    • First stocking, biosecurity SOPs signed off
    • Operator training, spares stocked
    • Performance guarantee testing against contract KPIs
    Common bottlenecks
    • · Stocking before biofilter is fully mature
    • · No trained operators on day one — quality risk in first cycle
    Operator readiness