How aquaculture consultants compare RAS suppliers and build bankable shortlists for clients

Published 2026-08-23 · 10 min read

Short answer

Consultants compare RAS suppliers by fixing one written design basis — species, standing biomass, peak daily feed load, design temperature, make-up water rate and discharge limits — and requiring every supplier to price against it. Offers are then normalised line by line: biofilter sizing basis, oxygen and CO2 capacity, solids removal, redundancy, controls, energy and scope boundary. A shortlist becomes bankable when two to four offers share the same assumptions, exclusions are written down, and the total evaluated cost includes freight, installation, spares and energy. FishMatch Group runs the RFQ and comparison workload behind the consultant; it does not design, build, finance, operate or certify projects.

Why RAS offers are harder to compare than any other package

A pump or an aerator can be compared on duty point and price. A recirculating system cannot, because the supplier is selling a set of assumptions: how much feed goes in each day, how much ammonia that produces, how much biofilter surface is needed to remove it at the design temperature, and how much water has to be replaced to keep nitrate and CO2 inside range. Change any assumption and the equipment list — and the price — changes with it.

That is why two offers for "the same" farm can differ by a large margin without either supplier being wrong. The comparison job is to remove the freedom to assume, then look at what remains.

  • Different feed loads. A supplier who assumes a lower peak feed rate sizes a smaller biofilter and quotes a lower number for a system that will not hold water quality at full stocking.
  • Different battery limits. Building, civils, external piping, electrical panels, freight and commissioning move in and out of scope between offers.
  • Different redundancy. Backup oxygen, standby blowers and N+1 pumping are sometimes included, sometimes optional, sometimes absent.
  • Different documentation. Without a mass balance, a sizing figure cannot be checked — and neither can the offer.

Step 1 — write the design basis before contacting anyone

One page is enough. Every figure that is unknown is written as a stated assumption so all suppliers price the same baseline and the client can see later what was assumed and by whom.

RAS design basis — minimum content

  • Species, strain, stocking size and target harvest size
  • Target annual tonnage, peak standing biomass and number of production batches
  • Peak daily feed load in kg/day and the feed protein level assumed
  • Design water temperature range and heating or cooling responsibility
  • Water source, salinity, alkalinity, hardness and any treatment already installed
  • Acceptable make-up water rate as a percentage of system volume per day
  • Discharge limits, effluent handling and sludge disposal route
  • Grid voltage, reliability, backup generation and available site power
  • Building status: existing, new-build in supplier scope, or client scope
  • Quarantine, biosecurity and effluent disinfection requirements

Sizing brackets can be produced first with the aquaculture calculators — biomass, feed load, oxygen demand and water exchange — and the assumptions behind them are documented on the calculator methodology page. These are planning brackets for an RFQ, not a substitute for detailed design.

Step 2 — compare on eight technical lines, not on price

Ask every supplier the same eight questions and record the answers in one table. The pattern of answers usually separates the shortlist before any commercial discussion starts.

LineWhat to ask forWhat the answer tells you
Biofilter sizingMedia type, specific surface area and the areal TAN removal rate assumed at design temperatureA supplier who quotes a removal rate and its source is engineering; one who quotes only a media volume is estimating
Oxygen supplyDelivery method, dissolved oxygen setpoint, transfer efficiency and capacity at peak feed loadCapacity should be tied to peak feed, not to tank volume
CO2 strippingStripping capacity, air-to-water ratio and target dissolved CO2 at design biomassFrequently the weakest line in low-cost offers
Solids removalDrum filter micron rating, hydraulic capacity, backwash water use and expected removal efficiencyBackwash volume drives the make-up water rate and the effluent load
RedundancyWhich duties are N+1, what happens on grid loss, and the backup oxygen hold timeRedundancy that is priced as an option should be listed as an exclusion, not a feature
ControlsControl philosophy, monitored parameters, alarm routing and remote access scopeAsk whether alarm hardware is included or expected from the client
EnergyInstalled kW and expected annual kWh per kg of production at design outputThe single largest OPEX driver in most RAS models
Scope boundaryCivil works, building, piping beyond skid limits, electrical panels, freight, installation, commissioning and trainingMost price gaps between offers are boundary gaps, not equipment gaps

Let the RFQ workload run behind you

One brief, private outreach to qualified RAS suppliers, a normalised comparison back to you. You keep the mandate and the recommendation.

Step 3 — verify what can be verified from the desk

Most claims can be tested for internal consistency without travelling. A mass balance, an equipment list and a power schedule that were produced for the same project agree with each other; documents assembled from a template usually do not.

Desk verification checks

  • Does the stated biofilter capacity match the TAN produced by the peak feed load?
  • Does the oxygen delivery capacity cover respiration plus biofilter demand at peak feed?
  • Does the installed kW in the power schedule match the equipment list?
  • Does the make-up water rate reconcile with drum filter backwash plus evaporation and sludge?
  • Are reference installations at comparable species, scale and temperature — with contactable operators?
  • Which major components are made in-house and which are bought in and re-badged?
  • Are commissioning, operator training and warranty response times priced, not promised?
  • Are spares for the first year listed with lead times?

Step 4 — turn the comparison into a bankable shortlist

A shortlist is bankable when a third party can read it without the consultant in the room. That means the evaluated cost, not the quoted cost, and the assumptions in writing next to it.

What belongs in the shortlist document

  • The single design basis all offers were priced against, with stated assumptions
  • Two to four offers side by side, scope-normalised to the same battery limits
  • Total evaluated cost: equipment, freight, duties, installation, commissioning, spares and first-year energy
  • Exclusions and open items per supplier, listed rather than absorbed into a note
  • Lead time, payment milestones, warranty duration and after-sales response commitment
  • Technical risk notes and what would change the ranking if an assumption moves
  • A clear recommendation with the reasoning behind it — signed by the consultant

Where a project is heading toward external funding, the same material feeds the documentation lenders usually expect — CAPEX build-up, OPEX model, production ramp and permit status. See financing readiness and the financing eligibility estimator. This is document structuring only — FishMatch Group does not lend, arrange, underwrite, approve or guarantee financing.

Where FishMatch Group fits

The consultant owns the design basis, the technical judgement and the client. FishMatch Group turns that basis into an RFQ pack, approaches qualified suppliers privately, keeps buyer and supplier identities confidential until both sides agree to proceed, and returns the offers normalised into one table. Many consultants use it as an unnamed sourcing desk and present the comparison under their own advisory report.

Background reading: the full method in how consultants find better suppliers, the consultant insight guides, and free working templates on the consultant downloads page.

Frequently asked questions

More consultant program answers

Send a RAS project for supplier matching

Submit the client project below. You keep the mandate; we run the sourcing and comparison workload.

1. About you
2. The client project
Species *
Suppliers / equipment needed *
3. How involved do you want us to be?
Optional details (helps us move faster)
We work through you. Your client is not contacted unless you ask us to.

Short answer

What do buyers need to know about How Consultants Compare RAS Suppliers Bankable Shortlists?

How Consultants Compare RAS Suppliers Bankable Shortlists affects both project cost and project risk, so it belongs in the specification stage rather than the purchasing stage. This page sets out what commercial buyers assess, what typically drives cost and lead time, and which questions to put to suppliers before signing. You can turn any of it into a confidential RFQ in a few minutes.

Who it is for:
Investors, operators and project developers specifying commercial systems
Cost drivers:
Capacity, water source, energy price, permitting and logistics
Next step:
Turn the requirement into a confidential RFQ
Cost to buyers:
No fee charged to the buyer

Before you request quotes

Equipment scope

What equipment does a commercial aquaculture project actually need?

A grow-out project typically needs holding infrastructure (tanks, ponds or cages), water movement (pumps, piping, valves), aeration or oxygenation, water treatment appropriate to the system, feeding equipment, grading and handling gear, monitoring and alarms, and backup power. RAS adds mechanical filtration, biofiltration, degassing, disinfection and tighter process control. Hatchery and processing scopes are specified separately.

Which equipment should be specified before requesting quotes?

Specify the items whose sizing changes everything downstream: design biomass and stocking density, water exchange or recirculation rate, oxygen demand at peak temperature, and installed pumping head. With those four fixed, suppliers can quote aeration, filtration, pumps and power on the same basis. FishMatch calculators produce these figures and attach them to the RFQ.

Can equipment be sourced in stages?

Yes, and phased procurement is common. The usual sequence is water supply and holding infrastructure, then aeration and treatment, then automation and monitoring, then processing and cold chain. Staging works when interfaces and capacity headroom are defined at the start; otherwise later phases force replacement rather than addition.

Supplier selection criteria

How should a buyer compare aquaculture suppliers?

Compare on evidence, not on presentation: delivered projects at a similar scale and climate, engineering support during design, lead time commitments, spare-part and service availability in your region, certification and testing documentation, payment and warranty terms, and willingness to quote against your specification rather than substituting a catalogue package.

What are the warning signs in a supplier quotation?

Treat these as review triggers: no itemised scope, guaranteed biological or financial performance, no named delivery terms or lead time, no spare-parts or service statement, unclear responsibility for installation and commissioning, and equipment sizing that does not reference your water temperature, oxygen demand or biomass targets.

How does FishMatch handle supplier selection?

FishMatch is an independent sourcing layer, not a manufacturer or reseller. Requirements are structured into a single technical RFQ and routed to relevant producers; buyers receive comparable offers without supplier identities being exposed before they choose to proceed. Selection stays with the buyer — FishMatch standardises the comparison basis.