How to plan a RAS project, step by step
Quick answer
Plan a RAS project in this order: confirm the market and price, choose the species and annual tonnage, secure a site with water, power and permits, write a design basis, build a budget with contingency, then compare at least three RAS suppliers on the same specification before signing.
1. Start from the market, not the technology
The most common reason RAS projects fail is not the filters or the pumps. It is a production plan that does not match a buyer who will pay enough per kilo. Before any design work, confirm who buys the fish, at what size, in what form and at what price.
Write down a target farm-gate price and a conservative sales volume. This single number decides how much capital the project can carry.
2. Choose species and scale
Species decide temperature, salinity, stocking density, growth time and equipment. Salmon, trout, barramundi, sea bream, grouper, tilapia and shrimp all need different system designs.
- Annual harvest target in tonnes
- Harvest size and number of batches per year
- Juvenile source: own hatchery or bought-in fingerlings/smolt
- Salinity and temperature range
3. Secure the site
A RAS needs reliable water for make-up and a stable power supply with backup. Check access roads, discharge rules, zoning and distance to your market before you pay for design.
4. Write a design basis
A design basis is a short document that fixes the key numbers: tonnage, species, feed load, water quality targets, redundancy level and building type. Suppliers quote against it, which makes their offers comparable.
5. Budget, financing and contingency
Build a CAPEX and OPEX model with at least 10–15% contingency. Include building, utilities, electrical backup, oxygen, commissioning, working capital for the first 18–24 months and staff training.
6. Compare suppliers on the same specification
Ask at least three RAS suppliers to quote the same design basis. Compare scope lines, guarantees, references, training and service, not only the headline price.
7. Permits, build and commissioning
Permits often take longer than construction. Start environmental and water permits early. Plan a staged start-up with biological commissioning before the first full stocking.