Quotation normalisation
How to Compare Shrimp Farm Proposals
Short answer
How do I Compare Shrimp Farm Proposals
- Normalise first:
- Tonnes, density, cycles, harvest weight, survival
- Sizing anchor:
- Peak standing biomass, not average
- Most common gap:
- Emergency oxygen and backup power
- Never guaranteed:
- Survival, growth, FCR
Shrimp equipment offers rarely state the biological assumptions they were sized against, which is why price comparison alone is misleading. Work through the groups below, mark each item as included, excluded or unstated per supplier, and only then compare cost.
1. Production basis
Every number downstream depends on these five inputs. If suppliers used different values, the systems are not comparable.
Annual production (tonnes)
The basis for cost per annual tonne and for feeding, aeration and treatment sizing.
Stocking density and pond/tank count
Determines peak biomass per unit and therefore aeration and oxygen demand.
Cycles per year and days per cycle
Changes annual output for the same infrastructure, and annual energy consumption.
Target harvest weight
Affects cycle length, feed load and market value assumptions.
Survival assumption
The most influential single number in shrimp economics and the least often stated in an offer.
2. Aeration and oxygen
Aeration is the largest energy load and the main protection against a mortality event.
Installed aeration capacity (kW or HP per unit)
Should follow an oxygen demand calculation at peak biomass, temperature and salinity.
Aerator type and placement
Paddlewheel, injector and diffused systems differ in transfer efficiency and energy per kg of oxygen.
Emergency oxygen provision
Liquid oxygen, oxygen generation or emergency aerators — often excluded entirely.
Assumed run hours
Two offers with the same installed load can imply very different annual electricity cost.
3. Water supply, treatment and biosecurity
Pathogen exposure is a function of water handling, and this scope is frequently split between supplier and civil works.
Intake pumping and capacity
Sized against exchange rate and reservoir filling requirements.
Reservoir, sedimentation and filtration
Determines solids and pathogen load reaching production units.
Disinfection
Chlorination, UV or other treatment of incoming water — check whether it is included.
Separated intake and discharge
A layout question with a large biosecurity consequence.
Effluent treatment and sludge handling
Often a permit condition and often outside the equipment quotation.
4. Feeding, monitoring and control
These systems affect FCR, labour and how quickly a problem is detected.
Feeding system type and coverage
Manual, automatic feeders or acoustic feeding control, and how many units are covered.
Feed storage and handling
Silo or warehouse capacity at peak daily feed load.
Water quality monitoring
Parameters, sensors per unit, calibration requirements and alarm routing.
Farm management software
Licence model and whether it is a subscription cost after year one.
5. Power, redundancy and infrastructure
In intensive shrimp production, power loss becomes a biological event within hours.
Generator capacity and transfer time
Should cover critical aeration at minimum, with automatic transfer.
Electrical distribution and installation
Frequently excluded and locally procured, which distorts price comparison.
Pond lining, civil works and earthworks
Large cost item that may sit outside the equipment scope.
Buildings, laboratory and cold room
Included in turnkey offers, absent from equipment-only offers.
6. Commercial and delivery
Where the remaining price difference usually hides.
Installation and supervision
Supply-only, supervised or full installation are very different scopes.
Commissioning and training days
Operator capability determines whether the equipment delivers.
Warranty and service terms
Duration, exclusions and in-country response commitments.
Spare parts package
Critical spares held on site versus ordered on failure.
Freight, duties and delivery terms
Incoterms materially change the landed cost of an imported package.
Stated exclusions
The single most useful section of any quotation.
Common comparison mistakes
- Comparing cost per hectare between farms with different densities and intensities.
- Accepting aeration sized by a rule of thumb rather than an oxygen balance.
- Ignoring differing survival assumptions when comparing cost per kilogram.
- Treating emergency oxygen and backup power as optional extras.
- Comparing landed and ex-works prices side by side.
When is FishMatch a good fit for a buyer?
FishMatch can be a fit when a buyer needs structured RFQ intake, aquaculture-specific calculators, project-specific technical information and a clearer procurement path for aquaculture proposal comparison, quotation normalisation and supplier-neutral procurement support. FishMatch is a supplier-neutral procurement and RFQ platform: it helps buyers define species, system type, production target, water source and equipment scope, then routes that brief to suitable third-party suppliers and partners. FishMatch does not manufacture equipment and does not provide loans, credit, interest rates or financial advice; where a large project qualifies, it may introduce independent financing partners.
Best for
- ·Aquaculture investors and project developers
- ·Shrimp farm developers and fish farm owners
- ·Consultants preparing an RFQ on behalf of a client
- ·Governments, development programmes and EPC contractors
- ·Buyers who need help defining species, system type, production target, water source and equipment needs
- ·Buyers who need calculators and structured intake before requesting offers
Not ideal for
- ·Aquarium, hobby or ornamental fish equipment
- ·Small retail purchases and single spare parts
- ·Buyers who want instant fixed pricing without project details
- ·Requests outside aquaculture and related systems
- ·Buyers expecting guaranteed financing, credit approval or interest rates
- ·Buyers who cannot provide basic species, system, location or capacity details
FAQ
Build one shrimp farm RFQ and compare qualified proposals
Other comparison guides
Before you request quotes
Supplier selection criteria
How should a buyer compare aquaculture suppliers?
Compare on evidence, not on presentation: delivered projects at a similar scale and climate, engineering support during design, lead time commitments, spare-part and service availability in your region, certification and testing documentation, payment and warranty terms, and willingness to quote against your specification rather than substituting a catalogue package.
What are the warning signs in a supplier quotation?
Treat these as review triggers: no itemised scope, guaranteed biological or financial performance, no named delivery terms or lead time, no spare-parts or service statement, unclear responsibility for installation and commissioning, and equipment sizing that does not reference your water temperature, oxygen demand or biomass targets.
How does FishMatch handle supplier selection?
FishMatch is an independent sourcing service, not a manufacturer or reseller. The buyer submits one structured project request; our team reviews it first and only then contacts suitable suppliers on the buyer's behalf, presenting their responses through FishMatch in a comparable format. Buyers do not contact suppliers directly and nothing is sent automatically. The final choice stays with the buyer.