Planning scenario · not a completed project

500 Ton Fish Farm: Project Cost & Equipment Plan

As a planning range, a 500 tonne/year fish farm costs about USD 6.0 million – USD 13 million as indoor RAS, USD 1.0 million – USD 3.0 million as aerated ponds, and USD 1.3 million – USD 6.0 million as cages, excluding land. Species, climate, site works and how much processing you include move the figure most. Use the calculator for your case, then compare real turnkey quotes through one RFQ.

Project at a glance

Production
500 tonnes/year
Annual feed (FCR 1.5)
750 tonnes
Average daily feed
2,055 kg/day
RAS standing biomass
≈ 175 tonnes
RAS tank volume (60 kg/m³)
≈ 2,917 m³
RAS oxygen demand
≈ 925 kg O₂/day
RAS energy use
≈ 1,250 MWh/year
Pond area (semi-intensive)
≈ 42 ha water surface
Fingerlings needed (800 g, 85% survival)
≈ 735 thousand/year

At 500 tonnes a year the project usually needs its own hatchery or a secured fingerling contract, a dedicated feed supply and at least basic on-site processing or a processor offtake. This is where turnkey and EPC contracts start to make sense.

Technology options compared

SystemIndicative CAPEXLandWaterPowerBest fit
RAS (indoor)USD 6.0 million – USD 13 million1.3–2.5 ha< 1–5% daily make-up≈ 1,250 MWh/yrWater-scarce or cold climates, premium species, near-city supply
Aerated pondsUSD 1.0 million – USD 3.0 million≈ 54 ha incl. dykesHigh: evaporation + exchange≈ 300 MWh/yr (aeration)Warm climate, cheap land, tilapia / catfish at scale
Cages (reservoir or sea)USD 1.3 million – USD 6.0 millionSmall shore base onlyNatural water bodyLow (boats, feeding)Licensed reservoir or sheltered sea site available

Equipment and construction, excluding land, working capital and taxes. Preliminary planning estimates — not quotes.

Equipment categories

  • Tanks or ponds / cages and moorings
  • Drum filters and moving-bed biofilters (RAS)
  • Oxygen generation (PSA/LOX), oxygen cones and diffusers
  • Pumps, pipework and UV / ozone
  • Aerators and blowers (ponds)
  • Automatic feeders and feed storage silos
  • Water-quality monitoring and alarms
  • Backup generators sized to critical load
  • Hatchery and nursery
  • Processing line and cold storage

Assumptions

  • Reference species tilapia, 800 g harvest, FCR 1.5.
  • RAS average density 60 kg/m³ and standing biomass ≈ 35% of annual output.
  • Oxygen ≈ 0.45 kg per kg of feed; RAS energy ≈ 2.5 kWh per kg produced.
  • Ponds ≈ 12 t/ha/yr with mechanical aeration.
  • CAPEX covers equipment and construction, excluding land, working capital and taxes. Planning estimates only — not quotes.

Questions buyers ask

How much does a 500 ton fish farm cost?

As a planning range, a 500 tonne/year fish farm costs about USD 6.0 million – USD 13 million as indoor RAS, USD 1.0 million – USD 3.0 million as aerated ponds, and USD 1.3 million – USD 6.0 million as cages, excluding land. Species, climate, site works and how much processing you include move the figure most. Use the calculator for your case, then compare real turnkey quotes through one RFQ.

How much feed does a 500 ton fish farm need?

At a feed conversion ratio of 1.5, producing 500 tonnes of tilapia needs about 750 tonnes of feed a year, or roughly 2,055 kg a day on average. Peak daily feeding is higher in warm months, so silo and feeding-system capacity should be sized for peak, not average.

How big should a RAS be for 500 tons a year?

At an average 60 kg/m³ and a standing biomass of about 175 tonnes, a 500 tonne/year RAS needs roughly 2,917 m³ of culture tanks, plus filtration and biofilter volume. Oxygen demand is around 925 kg per day. The supplier's design should confirm these figures for your species and temperature.

How much land does a 500 ton fish farm need?

An indoor RAS for 500 tonnes typically needs 1.3–2.5 hectares including buildings and roads. A pond farm needs about 54 hectares including dykes and canals. Cages need only a shore base, but require a licensed water body.

Turn this scenario into a real project

Send it as one RFQ. A FishMatch project lead reviews it and shortlists 3–5 suitable manufacturers, integrators or EPC contractors, so you receive comparable proposals.

Request complete turnkey proposals

Other project sizes

Short answer

What is the fastest way to get quotes for 500 Ton Fish Farm?

Submit one structured request for 500 Ton Fish Farm. FishMatch Group translates it into a technical RFQ, runs a confidential sourcing round with project-matched international suppliers, and returns comparable quotations. No fee is charged to the buyer, and your identity and project details stay private until you choose to proceed.

How it works:
One structured request, human-reviewed before any supplier outreach
Typical turnaround:
Depends on scope and site data; no turnaround is guaranteed
Confidentiality:
Supplier names are never exposed during evaluation
Cost to buyers:
No fee charged to the buyer