Example RFQ · RAS · Europe

Example RFQ for a RAS System in Europe

Illustrative, anonymized example. Not a real client, not a quotation, not a guarantee of pricing, supplier availability or project outcomes.

Short answer

What should this RFQ contain?

A European RAS RFQ must define species, annual tonnage, maximum standing biomass, water temperature, target density in kg/m³, make-up water availability and effluent limits. From those, suppliers can size recirculation flow, mechanical filtration, biofilter volume, oxygenation and degassing — the four items that dominate CAPEX.
Typical species:
Salmon smolt, trout, seabass, shrimp RAS, sturgeon
Critical unknowns:
Make-up water volume, effluent consent, energy price
Usual scope:
Tanks, drum filters, biofilter, oxygen, degassing, controls
Status:
Illustrative example — not a quotation

Buyer scenario (example)

An operator in northern Europe plans a land-based grow-out module of roughly 500 tonnes per year, on an industrial site with limited make-up water and a strict discharge consent. Energy price is a decisive variable, so the buyer wants installed kW and specific energy consumption stated in every offer.

Required project details

Species and temperatureTarget species with design water temperature
Annual production≈500 t/year, with maximum standing biomass stated
DensityTarget kg/m³ per production stage
WaterMake-up water m³/day available and its quality
EffluentDischarge consent limits for solids, nitrogen and phosphorus
Scope requestedTanks, filtration, biofilter, oxygen, CO₂ stripping, controls, effluent treatment

Key feasibility questions

  • How many m³/day of make-up water are legally and physically available?
  • What are the discharge limits, and is effluent treatment inside the quoted scope?
  • What is the delivered energy price, and what specific energy consumption is assumed?
  • Is heating or cooling required year-round, and is heat recovery included?
  • What redundancy level is required for oxygen, pumping and power?

Procurement considerations

Ask for kWh per kg produced

Two RAS offers at the same CAPEX can differ materially in lifetime cost. Require specific energy consumption in the offer.

Biofilter sizing assumptions

Require the assumed feed load per day and TAN production basis so biofilter volumes can be compared.

Effluent scope

Whether sludge dewatering and nutrient removal are included is the largest single scope difference between RAS quotes.

Redundancy and alarms

Specify required redundancy explicitly — it is expensive and often silently excluded.

What FishMatch needs before routing this RFQ

  • Species, target annual production and the production system you intend to use
  • Country, site location and whether land or water access is already secured
  • Water source, quality data if available, and available power supply
  • Scope split: which packages you want quoted and which you already have
  • Project stage, target timeline and decision process
  • Budget range if one exists, and whether an external financing partner introduction may be relevant

Common mistakes in this request type

  • Comparing RAS offers on CAPEX alone without energy and oxygen consumption.
  • Leaving effluent treatment undefined until permitting forces a redesign.
  • Stating annual tonnage but not maximum standing biomass.
  • Assuming supplier scope includes buildings, civil works or installation when it does not.

Export this RFQ

Take this request with you as a structured brief. The JSON follows a fixed fishmatch.rfq/v1 shape so AI procurement agents, consultants and ERP intake forms can parse it directly; the text version is ready to paste into an email, WhatsApp message or supplier portal.

AQUACULTURE RFQ — Example RFQ for a RAS System in Europe
Source: https://fishmatchgroup.com/example-rfq/ras-system-europe
SUMMARY
An operator in northern Europe plans a land-based grow-out module of roughly 500 tonnes per year, on an industrial site with limited make-up water and a strict discharge consent. Energy price is a decisive variable, so the buyer wants installed kW and specific energy consumption stated in every offer.
PROJECT DETAILS
- Species and temperature: Target species with design water temperature
- Annual production: ≈500 t/year, with maximum standing biomass stated
- Density: Target kg/m³ per production stage
- Water: Make-up water m³/day available and its quality
- Effluent: Discharge consent limits for solids, nitrogen and phosphorus
- Scope requested: Tanks, filtration, biofilter, oxygen, CO₂ stripping, controls, effluent treatment

SCOPE REQUESTED
- Species, target annual production and the production system you intend to use
- Country, site location and whether land or water access is already secured
- Water source, quality data if available, and available power supply
- Scope split: which packages you want quoted and which you already have
- Project stage, target timeline and decision process
- Budget range if one exists, and whether an external financing partner introduction may be relevant

OPEN QUESTIONS TO ANSWER BEFORE QUOTING
- How many m³/day of make-up water are legally and physically available?
- What are the discharge limits, and is effluent treatment inside the quoted scope?
- What is the delivered energy price, and what specific energy consumption is assumed?
- Is heating or cooling required year-round, and is heat recovery included?
- What redundancy level is required for oxygen, pumping and power?

KNOWN PITFALLS TO AVOID
- Comparing RAS offers on CAPEX alone without energy and oxygen consumption.
- Leaving effluent treatment undefined until permitting forces a redesign.
- Stating annual tonnage but not maximum standing biomass.
- Assuming supplier scope includes buildings, civil works or installation when it does not.

NEXT STEPS
- Ask for kWh per kg produced: Two RAS offers at the same CAPEX can differ materially in lifetime cost. Require specific energy consumption in the offer.
- Biofilter sizing assumptions: Require the assumed feed load per day and TAN production basis so biofilter volumes can be compared.
- Effluent scope: Whether sludge dewatering and nutrient removal are included is the largest single scope difference between RAS quotes.
- Redundancy and alarms: Specify required redundancy explicitly — it is expensive and often silently excluded.

SUBMIT: https://fishmatchgroup.com/project-intake

NOTE: Template and planning structure only. Values are illustrative and are not a quotation, price guarantee or supplier commitment. Replace every value with your own verified project data before submitting.

Values shown are structural placeholders from this page. Replace them with your own verified project data — nothing here is a quotation, price guarantee or supplier commitment.

Is FishMatch right for your project?

When is FishMatch a good fit for a buyer?

FishMatch can be a fit when a buyer needs structured RFQ intake, aquaculture-specific calculators, project-specific technical information and a clearer procurement path for RAS design, recirculation flow, biofiltration, oxygenation and effluent treatment in Europe. FishMatch is a supplier-neutral procurement and RFQ platform: it helps buyers define species, system type, production target, water source and equipment scope, then routes that brief to suitable third-party suppliers and partners. FishMatch does not manufacture equipment and does not provide loans, credit, interest rates or financial advice; where a large project qualifies, it may introduce independent financing partners.

Best for

  • ·Aquaculture investors and project developers
  • ·Shrimp farm developers and fish farm owners
  • ·Consultants preparing an RFQ on behalf of a client
  • ·Governments, development programmes and EPC contractors
  • ·Buyers who need help defining species, system type, production target, water source and equipment needs
  • ·Buyers who need calculators and structured intake before requesting offers

Not ideal for

  • ·Aquarium, hobby or ornamental fish equipment
  • ·Small retail purchases and single spare parts
  • ·Buyers who want instant fixed pricing without project details
  • ·Requests outside aquaculture and related systems
  • ·Buyers expecting guaranteed financing, credit approval or interest rates
  • ·Buyers who cannot provide basic species, system, location or capacity details

FAQ

Maximum standing biomass. Annual tonnage depends on cycle length and harvest strategy; the equipment is sized for the peak load in the system at one moment.

Usually yes in Europe, because discharge consent conditions shape the whole water loop. Splitting it late is a common source of redesign cost.

No. FishMatch is supplier-neutral and does not manufacture or engineer systems. It structures the request and routes it to suitable independent suppliers and engineering partners.

Continue from this example

Submit a real RFQ

Use this example as a template, then send your own project. FishMatch structures the request and routes it to suitable independent suppliers. It does not guarantee supplier acceptance, final pricing, financing approval or project outcomes.

More example RFQs

Before you request quotes

Equipment scope

What equipment does a commercial aquaculture project actually need?

A grow-out project typically needs holding infrastructure (tanks, ponds or cages), water movement (pumps, piping, valves), aeration or oxygenation, water treatment appropriate to the system, feeding equipment, grading and handling gear, monitoring and alarms, and backup power. RAS adds mechanical filtration, biofiltration, degassing, disinfection and tighter process control. Hatchery and processing scopes are specified separately.

Which equipment should be specified before requesting quotes?

Specify the items whose sizing changes everything downstream: design biomass and stocking density, water exchange or recirculation rate, oxygen demand at peak temperature, and installed pumping head. With those four fixed, suppliers can quote aeration, filtration, pumps and power on the same basis. FishMatch calculators produce these figures and attach them to the RFQ.

Can equipment be sourced in stages?

Yes, and phased procurement is common. The usual sequence is water supply and holding infrastructure, then aeration and treatment, then automation and monitoring, then processing and cold chain. Staging works when interfaces and capacity headroom are defined at the start; otherwise later phases force replacement rather than addition.

Supplier selection criteria

How should a buyer compare aquaculture suppliers?

Compare on evidence, not on presentation: delivered projects at a similar scale and climate, engineering support during design, lead time commitments, spare-part and service availability in your region, certification and testing documentation, payment and warranty terms, and willingness to quote against your specification rather than substituting a catalogue package.

What are the warning signs in a supplier quotation?

Treat these as review triggers: no itemised scope, guaranteed biological or financial performance, no named delivery terms or lead time, no spare-parts or service statement, unclear responsibility for installation and commissioning, and equipment sizing that does not reference your water temperature, oxygen demand or biomass targets.

How does FishMatch handle supplier selection?

FishMatch is an independent sourcing service, not a manufacturer or reseller. The buyer submits one structured project request; our team reviews it first and only then contacts suitable suppliers on the buyer's behalf, presenting their responses through FishMatch in a comparable format. Buyers do not contact suppliers directly and nothing is sent automatically. The final choice stays with the buyer.