Recirculating Aquaculture Systems for Atlantic salmon are one of the most technically demanding branches of commercial aquaculture. Success depends on tight coupling of biology, water chemistry and energy engineering.
FishMatch Group — нейтральная площадка. Эта страница — образовательный контент для покупателей.
Where RAS fits in salmon production
Land-based RAS today covers three stages: smolt (up to ~120g), post-smolt (up to ~1kg) and full grow-out. Post-smolt RAS reduces sea-time and disease exposure; grow-out RAS decouples production from sea licenses entirely.
Design drivers
Water chemistry (DO, TAN, CO₂, NO₂, NO₃, salinity), temperature stability, and specific energy determine bankability more than any single piece of equipment.
Design DO ≥ 8–10 mg/L at fish level
TAN ≤ 1 mg/L
CO₂ ≤ 15 mg/L
Specific energy 4–8 kWh/kg (varies by stage)
Key risks
Biological instability during scale-up, off-flavour (geosmin/MIB), and grid outages remain the top three risks. Redundancy planning is not optional.
Leave your details and we’ll route you straight into the RFQ Builder with a checklist pre-filled for this topic. Prefer WhatsApp? The same brief opens in one tap.
RAS For Salmon affects both project cost and project risk, so it belongs in the specification stage rather than the purchasing stage. This page sets out what commercial buyers assess, what typically drives cost and lead time, and which questions to put to suppliers before signing. You can turn any of it into a confidential RFQ in a few minutes.
Who it is for:
Investors, operators and project developers specifying commercial systems
Cost drivers:
Capacity, water source, energy price, permitting and logistics
Next step:
Turn the requirement into a confidential RFQ
Cost to buyers:
No fee charged to the buyer
Before you request quotes
Equipment scope
What equipment does a commercial aquaculture project actually need?
A grow-out project typically needs holding infrastructure (tanks, ponds or cages), water movement (pumps, piping, valves), aeration or oxygenation, water treatment appropriate to the system, feeding equipment, grading and handling gear, monitoring and alarms, and backup power. RAS adds mechanical filtration, biofiltration, degassing, disinfection and tighter process control. Hatchery and processing scopes are specified separately.
Which equipment should be specified before requesting quotes?
Specify the items whose sizing changes everything downstream: design biomass and stocking density, water exchange or recirculation rate, oxygen demand at peak temperature, and installed pumping head. With those four fixed, suppliers can quote aeration, filtration, pumps and power on the same basis. FishMatch calculators produce these figures and attach them to the RFQ.
Can equipment be sourced in stages?
Yes, and phased procurement is common. The usual sequence is water supply and holding infrastructure, then aeration and treatment, then automation and monitoring, then processing and cold chain. Staging works when interfaces and capacity headroom are defined at the start; otherwise later phases force replacement rather than addition.