Shrimp processing plant RFQ: what every bidder should price
Before requesting a quote, give each bidder the same peak intake, product mix and net finished output by shift. Set the cold-chain handovers, water and discharge boundary, food-safety responsibilities and acceptance tests. Have each bidder show where its scope stops and how it will demonstrate performance with your product.
FishMatch Group editorial team · Editorial date

State raw input and saleable output separately
Start with a receiving calendar and a product schedule, not the annual harvest total. For each product, give species, size/count basis (per kg or per lb), head-on or peeled form, raw or cooked status, retail or bulk pack and chilled or frozen dispatch. Flag whether products run together or on separate shifts. Use actual working time after sanitation, changeovers and planned stops; state the peak delivery window separately.
Example only: 8 tonnes of raw shrimp over five effective hours means an average raw-line duty of 1,600 kg/h during that window. It is not a guarantee or a freezer rating. Set an independent finished-product target by SKU, record measured trial losses at each stage and reconcile rejects, shell and head fractions, glaze, and packed net weight. Ask both bidders to state the bottleneck for the same SKU mix.
Set the cold-chain handovers and pack basis
At receiving, state how lots arrive, expected temperature evidence, ice and meltwater handling, lot identification and who can place nonconforming material on hold. Map the time between unloading, grading, processing and freezing. For IQF or block freezing, ask for kg/h for the specified pack, size and inlet condition at the specified product outlet condition. Do not compare rated capacity with tested capacity at different conditions.
Codex’s fishery-products code describes shrimp processing, freezing and glazing. If the buyer requires glaze, specify how it is measured, and compare net product excluding glaze, glazed weight and gross shipping weight as separate values. Ask for label and lot-code samples, stock rotation and a trace from pack back to raw lot. Define cold-store peak inventory, dwell time, pallet positions, airflow and dispatch peaks separately from freezer duty. Assign responsibility for temperature records and handover to the carrier.
Put water, wastewater and utilities on the scope drawing
List where water and ice contact product and who verifies suitability, capacity and storage. Separate average from simultaneous peak demand for water, ice, refrigeration, electrical supply and hot water or steam. Put drains, connection points, control interfaces and backup loads on the same drawing; call out what the equipment installer must provide and what belongs to the building contractor.
The IFC fish-processing guidelines discuss solids recovery and process wastewater. Have the site team characterize the volume and composition of cleaning and process streams, including peak flow, organic load, solids and, where relevant, salinity. Itemize solids capture, treatment, sludge handling, sampling points and the receiving system. Confirm discharge requirements locally before selecting treatment; neither a generic equipment list nor these guidelines is a permit.
Set quality controls and prove them during commissioning
Use Codex as a general HACCP framework: document process flow, prerequisite hygiene measures and site-specific hazard assessment. Model raw and cooked movements separately, including people, equipment and drains. Assign responsibility for validation, monitoring, calibration, corrective action and release. Do not designate a control point or set a limit solely because a supplier includes a sensor.
Write the acceptance protocol before tenders close. Separate factory checks from site tests with the buyer’s product, pack and shift pattern. Record sustained throughput on the agreed net basis, outlet product condition, utilities at the defined boundaries, lot traceability and agreed recovery tests. State who supplies product, instruments and witnesses, what counts as a failed run and who pays for a retest. Require operating and cleaning instructions, training and handover records.
Compare bids without endorsing a vendor
Keep one revision of the brief for every bidder. Request a line-by-line compliance and exclusions list; compare raw intake, net packed output, freezer conditions and cold-store performance on the same basis. Then compare civil, electrical and drainage interfaces; accepted utility loads; wastewater responsibilities; spare parts and training; and tests, remedies and total installed scope. Record assumptions and questions in the same clarification log. An unpriced interface is not a saving.
Questions before you request quotes
Is annual volume enough to size the line?
No. Peak delivery and effective run time set the intake duty; net product targets and operating conditions set each downstream duty.
Can a freezer quote cover the entire cold chain?
Not on its own. Agree receiving, freezing, storage, dispatch and transfer-of-custody limits separately, then assign an owner to each.
Can a supplier provide an approved HACCP plan with the equipment?
Equipment data and test records can support the plan. The operator’s qualified team must assess the actual process and verify applicable requirements; an equipment quote is not an approval.