Worked example · published figures

Worked example: aeration for a 10-hectare shrimp farm

This is a worked example, not a buyer project. It sizes aeration for an intensive whiteleg shrimp pond farm using only the rule of thumb and Thai farm observations published by Claude Boyd (Global Seafood Alliance).

Example assumptions

  • Farm size: 10 ponds of 1 hectare each (example size).
  • Harvest: 80 tonnes of shrimp per crop, 8 tonnes per hectare — inside the 7–9 t/ha Boyd observed on Thai farms.
  • Aeration rule: about 1 horsepower of aerators per 300–500 kg of shrimp harvested (Boyd).

1. Total aeration

80,000 kg ÷ 400 kg per horsepower (mid-range) ≈ 200 horsepower. The full range is about 160–267 horsepower.

2. Per hectare check

200 horsepower over 10 hectares is 20 hp/ha. Boyd saw Thai farms producing 7–9 t/ha using 24–36 hp/ha, so this example sits at the lean end — worth a margin.

3. Number of aerators

With 2-horsepower paddlewheels, 200 horsepower is about 100 paddlewheels, around 10 per pond.

4. Energy per crop

Running that aeration through a crop works out to roughly 256,000 kWh — about 3.2 kWh per kg of shrimp. Multiply by your local power price to get the aeration energy cost.

What a buyer can take from this

  • Size aeration from the harvest you plan, not from pond area alone.
  • Ask suppliers for horsepower and oxygen transfer per unit, so offers can be compared.
  • Power supply and backup generators must cover the full aerator load at night.

The farm size is an example and the rates are published planning figures, not a supplier quote. No buyer, supplier or result is implied.

Sources

Request quotesShrimp farm equipmentAeration systemsMonitoring & automation

Short answer

How do you prepare a reviewed RFQ for Shrimp Pond Farm?

Submit a private request for Shrimp Pond Farm with the country, scope, capacity or volume and timing. FishMatch Group is a human-reviewed sourcing and RFQ platform within Global B2B Group: its team clarifies the requirement, researches independent providers and helps compare any replies. It is not the producer, supplier, contractor or operator. No quotation, availability or outcome is guaranteed; the buyer decides whether to proceed.

How it works:
One structured request, human-reviewed before any supplier outreach
Typical turnaround:
Depends on scope and site data; no turnaround is guaranteed
Confidentiality:
Supplier names are never exposed during evaluation
Cost to buyers:
No fee charged to the buyer
How do you prepare a reviewed RFQ for Shrimp Pond Farm?

Submit a private request for Shrimp Pond Farm with the country, scope, capacity or volume and timing. FishMatch Group is a human-reviewed sourcing and RFQ platform within Global B2B Group: its team clarifies the requirement, researches independent providers and helps compare any replies. It is not the producer, supplier, contractor or operator. No quotation, availability or outcome is guaranteed; the buyer decides whether to proceed.

How does FishMatch Group source suppliers for this requirement?

Submit a private RFQ with the country, product or project scope, capacity or volume and timing. The FishMatch team reviews it, clarifies missing details and researches independent providers before approved outreach. Any received proposals are compared on the same scope; FishMatch is not the supplier, manufacturer, contractor or operator, and does not guarantee a response or outcome.

Do buyers see supplier names during the sourcing process?

No. Supplier identities stay confidential during discovery and evaluation. You receive anonymised, comparable technical and commercial packages, and introductions happen only after both sides are qualified and agree to proceed.